Loading...
SW0001-MP031010RIVERCHASE SIDEWALK S W 00 -01 PACHECO KOCH ENGINEERING Otr 3, 2001 Qtr 4, 2001 Qtr 1, 2002 Qtr 2, 2002 Qtr 3, 2002 Qtr 4, 2002 - Sep Qtr 1, 2003 Qtr 2 2003 Qtr 3, 2003 ID Task Name _ Jun - Jul Aug Sep Oct Nov Dec - Jan. Feb Mar Apr May Jun Jul Aug Oct Nov - Dec Jan Feb Mar Apr May Jun Jul Aug'. Sep 1 DESIGN PHASE 2 Design 3 Advertisement 4 Bid Opening 1016 5 City Council � I � I j . 12 1 1 0 6 .'. PERMITS 7 TAS .9N0 8 RIGHT -OF -WAY 9 City of Irving I i 10 Response Received 10110 11 Approved . 5/22 12 Dallas Water Utilities 13 Approved 6/6 I 14 TXU Electric 16 Response Received 10/9 16 Res Response Received P I . 7/23 17 Acquired by City 3112 18 Lot 11 River Ridge Addition 19 Acquired by City 6/6 20 HOA River Ridge Addition 21 Acquired by City 22 CONSTRUCTION 9/30 � eeting Ili _ 1/6 Proceed 25 Construct Project: SW 00 -01 Task Milestone . Summary ^ Deadline Date: Fri 10/10/03 Page 1 RIVERCHASE SIDEWALK SW 00 -01 PACHECO KOCH ENGINEERING 2 Design On October 9, 2001 TXU decided not to approve the permit. Sidewalk will need to be redesigned to avoid conflict with TXU transmission lines. Working with TXU to resolve issue. 7 TAS Plans were submitted by Pacheco Koch. Minor comments were incorporated into the final bid set. 9 City of Irving First request sent on September 12, 2001. Second letter sent with revised plans on May 7, 2002, 10 Response Received City of Irving did not approve permit - would not allow elevated portion of sidewalk within their easement. 12 Dallas Water Utilities First letter sent on September 12, 2001. Second letter send with revised plans on May 7, 2002. 14 TXU Electric TXU denied request for use of easement. The sidewalk must cross beneath the wires within a 50 -foot radius of the transformer tower. TXU sent letter dated March 20, 2002 which provided acceptable areas for the crossing of the TXU easements. City sent letter March 22 with exhibit showing two options for the sidewalk layout. 16 Response Received Did not approve the permit. 16 Response Received Did not approve the permit. 17 Acquired by City September 9, 2002 - TXU requested revised plat, wrong page number. PKCE revised. 23 Preconstruclion Meeting Contractor requested that the Notice to Proceed be delayed. The work limits are not easily accessible because of all the recent rain. 26 Construction WEEK 1 (Apr. 21 -26) No activity . WEEK 2 (Apr. 28 - May 2) Graded area for the concrete on -grade sidewalk along Starleaf Drive. WEEK 3 (May 6 - 9) No activity. WEEK 4 (May 12 - 16) No activity . WEEK 5 (May 19 -23) No activity . WEEK 6 (May 26 - 30) Subcontractor for the elevated sidewalk started work on May 31. WEEK 7 (June 2 -6) No activity. WEEK 8 (June 9 -131 Contactor started the installation of the helical piers - installed approximately three - fourths of the piers. WEEK 9 (June 16 - 20) Installed the joists, 4 "x4" posts, and decking, starting from Starleaf to the 2nd turn in the sidewalk. WEEK 10 (June 23 - 27) Worked on the installation of the horizontal rails. WEEK 11 (June 30 - July 4) Worked on the installation of the horizontal rails and 4X4 wiring. WEEK 12 (July 07 -11) Worked on the installation of the horizontal rails and 4x4 wiring. WEEK 13 (July 14 - 18) Worked on the installation of piers, headers, and joists from 2nd PI to 40 feet west of Bradford. Received information from the engineer for the installation of a 2x6 on top of the 44 posts. WEEK 14 (July 21 - 26) Poured the five foot concrete sidewalk along Starleaf. Constructed the handicapped ramps. WEEK 16 (July 28 -Aug. 1) Page 2 RIVERCHASE SIDEWALK SW 00 -01 PACHECO KOCH ENGINEERING Poured the eight foot sidewalk. Worked on the installation of the elevated sidewalk. Complete to within 40 feet of Bradford. WEEK 16 (Aug.4 A) Formed the eight foot sidewalk at the beginning of the elevated sidewalk and poured. Holly Barber, the school principle, wanted to know if the sidewalk would be completed before school started so she could sent letter to the students. Contractor assured us that the sidewalk would be complete. WEEK 17 (Aug. 11 - 15) Completed the elevated portion of the sidewalk. Formed and poured the additional five foot sidewalk along MacArthur, that was added as change order. Waiting on a price from the contractor for installing a top rail along the elevated sidewalk. Page 3