Coppell Ind 2-CS031002
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM: PD-185R-LI, Coppell Industrial Addition (Tradepoint), zoning change
request on 98.84 acres of property from PD-185-LI to PD-185R-LI to attach
a Detail Site Plan to allow for an approximate 350,183 square-foot expansion
to the existing 600,000 square-foot building on Lot lR and the development
of an approximate 952,094 square-foot office/warehouse building on Lot 2
located 50' east of Royal Lane; north of Bethel Road, at the request of
Hillwood Fund No.1, LP.
STAFF REP.: Marcie Diamond PROJECT ID# PD-03..{i9
DRC DATE: September 25, 2003 and October 2, 2003
CONTACT: Teresa M Turner, E.L T., Graduate EnJ[ineer (972)304-3681
COMMENT STATUS: PRELIMINARY -/FINAL REVISED
f'~ICTER P&Z
1. As I believe you are aware, the fire line for Building 1 must be fixed.
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM: Coppelllndustrial Addition (Tradepoint), Lots lR and 2, Block A, Replat
and Final Plat, being a replat of Lot 1, Block A, and a Final Plat of Lot 2,
Block A, on 98.84 acres of property to allow for an approximate 350,183
square-foot expansion to the existing 600,000 square-foot building on Lot lR
and the development of an approximate 952,094 square-foot office/warehouse
building on Lot 2 located 50' east of Royal Lane; north of Bethel Road, at the
request of Hillwood Fund No.1, LP.
STAFF REP.: Marcie Diamond PROJECT ID# FP-03-70
DRC DATE: September 25, 2003 and October 2, 2003
CONTACT: Teresa M Turner, E.L T., Graduate Engineer (972)304-3681
COMMENT STATUS: PRELIMINARY ,(FINAL REVISED
f'~J:'TER P&Z
1. In preparation for the future improvements to Bethel Road, additional ROW dedications and
temporary easements are n~ed. I have included the necessary documents to be included on
the plat. Any ROW dedications will be credited to the roadway impact fee assessment.
2. A firelane easement cannot overlap an existing drainage easement - work with TranSystems.
3. Additional easements may be required during the engineering review process.