Champions-LR031110November 10, 2003 Project No. 10314 Report No. 14 Smith Commercial Contracting 14350 West Sylvanfield Houston, Texas 77014 ATTN: Mr. Patrick Popowitz Re: Structural Steel Inspection Champion School of Real Estate Denton Tap Road and Natches Trace Drive Coppell, Texas Gentlemen: Transmitted here are the results of the structural steel inspection performed at the referenced site for Reed Engineering Group, Ltd. on October 29, 2003, by Allied Inspection Service. If you have any questions, do not hesitate to call. Sincerely, REED ENGINEERING GROUP, LTD. Original Signed By Ronald F. Reed, P.E. RFR/cn Copies submitted: (1) Smith Commercial Contracting/Mr. Patrick Popowitz (1) Jacobs & Associates/Mr. David Koslan (1) City of Coppell/Mr. Larry Davis 2424 STUTZ DR · SUITE 400 - DALLAS, TX 75235 · TEl. [214] 350 5600 · FAX [214] 350 0019 Tim Glazier 817-501-1042 Allied Inspection Service P.O. Box 1143 Burleson, Texas 76097 Cecil McKinney 817-501-1650 Project Name: CHAMPIONS/School of Real Estate Date of Service: 10/29103 Coppell, Texas Lab Number: 8091.3 Client: Reed Engineering Group Attention: Keith Atkins 2424 Stub[ Ste. 400 Page: Dallas, Texas 75235 1 of 2 All inspections are performed in accordance with Governing Contract documents and applicable Structural Codes and standards Location (s) Inspected Structural Steel Framing at lines 1 to 9, gdds A to M. Inspector Comments: Results are as follows, As requested a visual inspection of the project noted above was conducted. 1) Column to pier anchor bolts comply for tensioning and nut engagement (base plates have not been grouted yet). *2) Bolted connections (beam to beam and beam to column) are still in progress of bolt installation and bolt tensioning. Some of the beam bolt holes have been field torah enlarged. Engineer please advise. *3) Several joist have less than 2 1/2" beadng. Engineer please advise. *4) The joist bdd~ling was not installed as per structural drawin~ls. Engineer please advise. '5) The perimeter angle to beam connections was not welded as per detail 01/S-4. Welds were spaced at36" in lieu of 12". *6) The installation of the knee braces (Ref. 04/S-4) is still in progress. *7/ The erection of the clerestory framing (Ref. 02JS-2) is still in progress. '8) The bottom chord of the joist at 21E does not extend to the column stabilizer plate. Engineer advise. Technician Allied Inspection Representative This report is for the exclusive use of our client and shall not be modified or reproduced without written approval of said client. Project Name: Champion School of Real Estate Date of Service: Lab Number: Client: Reed Attention: Page: 10/29/03 8091.3 2 of 2 All inspections are performed in accordance with Governing Contract documents and applicable Structural Codes and standards Location (s) Inspected Inspector Comments: *9) The column stabilizer plate for the bottom chord of the joist at 6/K was not present (missin~l). Engineer please advise. Welder qualifications were not available for review. Note: Metal roof deck installation is in progress. *Open items Cecil Mckinney CWl 99121311 Technician Allied Inspect'on Represer~'e