TO:
FROM:
DATE:
RE:
CC:
Ken Griffin, P.E., Suzan Taylor
Chris Moorman
November 17, 2003
Bethel Road II Construction
Tricia Hatley, P.E.
Project Updates:
Geotechnical investigation has been completed and the final draft of the geotechnical report is in
progress.
Received hydraulic data from Transystems on the channei improvements upstream of the cuivert
on Coppell Road.
Vertical alignment for Coppell Road has been established and making preiiminary adjustments for
siopes.
Tasks and deliverables tor the next two weeks:
Final Revision of Downtown Layout for Dec. 8 City Council meeting.
Date:
Dec. 4, 2003
March 3, 2004
Deliverable:
Final Right-at-Way map
Preliminary Plan Submittal