Loading...
ST0003-MP030801 ,\ t._ " ., ~\J~ , (, '. l\J.";\l cV (1\ W\I v~.> ~, ~ \iClkVIJi~ e,l PROJECT SCHEDULE COPPELL ROAD IMPROVEMENTS Activity Completion Date Notice. To-Proceed July I, 2003 Surveying for Design October 3, 2003 Geotechnical Investigation October 3, 2003 Schematic Design Submittal December 3, 2003 Schematic City Review Complete December 17,2003 Preliminary Design Submittal April 16, 2004 Preliminary City Review Complete April 30, 2004 Right-of-Way Exhibits Complete July 30, 2004 Final Design Submittal July 30, 2004 Final City Review Complete August 13, 2004 Final Plans Complete August 31, 2004 SWPPP Complete August 31, 2004 Right-of-Way Acquisition Complete February 28, 2005 Franchise Utility Relocations Complete May 31, 2005 Advertise for Bids April 3, 2005 Receive Bids April 21, 2005 Contract A ward May 10,2005 Surveying for Construction Control Complete May 31, 2005 Begin Construction June], 2005 Complete Construction May 31, 2006 Record Drawings June 30, 2006 $ 1_90 -0;' 08/01/03