WA9901-CN031113 CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT:
CONTRACTOR:
OWNER:
CHANGEORDER NO.:
Meadowcreek / Rolling Hills Water Line Installation Project # WA 99-01
Site Concrete, Inc.
City of Coppell
Two (2)
DATE: October 31, 2003
Item Description Quantity Unit Unit Price
Total
ADD:
New Sawcut (full depth) 27 LF 3.45
New Concrete Removal 474 SF 1.15
New Concrete Replacement 474 SF 4.60
Total Revision to Contract Amount
93.15
545.10
2,180.40
$2,818.65
Previous contract amount
Net increase in contract amount
Revised contract amount
Net increase in contract time of completion
Revised Contract time of completion
$353,200.00
$2,818.65
$356,018.65
N/A
N/A
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.