ST9304-CS 961115PROJECT STATUS November 15, 1996 Belt Line Road: Design: Preliminary Plans: 75% complete Final Plans: 50% complete anticipate 100% in March 97 Right-of-way: · 4 parcels and 5-10 slope and drainage easements to acquire · Right-of-way plans provided by end-96 · Acquisition to begin early-97 Construction: · Utility relocation begin early-97 · Actual construction begin mid-97 Issues: · No major issues at this time Summary: · Best Case: · Realistic: begin construction mid-97 with no major issues should begin mid-97 SUBMITTED BY: ~ f Directo o Public Works/City Engineer