ST9502-CN 960322PROJECT: CONTRACTOR: OWNER: CHANGE ORDER NO.: CITY OF COPPELL CHANGE OR EXTRA WORK ORDER DELETE: ADD: Item 1 2 4 Town Center Drive & Town Center Blvd. / ST 95-02 Site Concrete, Inc City of Coppell 1 DATE: March 22, CHANGE OR EXTRA WORK TO BE DONE 1996 Description Quantity Unit Unit Total Price 8" SS Pipe 260 LF 14.75 ($3,835.00) 4' Dia. Manhole 1 EA 1,250.00 $1,250.00 8" D.I. SS Pipe 10 LF 46.50 $465.00 10" SS Pipe 250 LF 20.25 $5,062.50 Total Revision to Contract Amount $2,942.50 Previous contract amount Net increase in contract amotmt Revised contract amount Net increase in contract time of completion Revised Contract time of completion $ 444,214.25 $ 2,942.50 $447,156.75 N/A N/A The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. R~~.~d~.......,e~,~~e ~ity Engineer: ~Accep d by the Owner: Date: ,~' AS. ~ b Date: