Loading...
Bank One-LR030910REPORT OF REINFORCING STEEL OBSERVATION 'lrerracon Dallas, Texas 75247 Date of Service: Client No.: Client: 09/10/03 17776 Bank One Texas NA 8111 Preston Suite 250 Dallas, TX 75225 Report No.: Project No.: Project: 94031289.0041 9403 [ 289 Bank One - Coppell TX 616 North Denton Tap Rd Coppell, TX Services: Drawings Utilized: Observe placement of reinforcing for compliance with furnished drawings. PROJECT DATA Approved 06/05/03, Pages C2, C7 Locations/items Observed: W half of S drive, parking W of building & approach to Denton Tap Test Method: Visual Observation REPORT OF OBSERVATION ITEMS OBSERVED CORRECT INCORRECT ITEMS OBSERVED CORRECT INCORRECT ITEMS OBSERVED CORRECT INCORRECT Placing Drawings Approved X Lenglh and Shape X Column Tie Spacing & Type Bar Size X Proper Placement X Stirrup Spacing & Type Bar Grade X. Propedy Tied X Rebar Clean X Dowel Bars in Place X Welde0 Splices Form Clean X Proper Supports X Mechanical Splices Number of Bars X Proper Cover X Lapped Splices X Discrepancies/Comments: The following discrepancies were noted and not corrected at the time of this observation. 1. No 4 1/2 inch metal sleeves were at the expansion joint. 2. An extra reinforcing bar was placed in top of the curb, not on prints. Field Results Report To: Ken Tonne Technician: B. Thomas Report Distribution: (1) Bank One Texas NA (1) City of Coppell TX (1) Aguirre Building Systems (1) City of Coppell TX 'lrerracon Hussein H. Abusaad, P. E. Senior Project Manage 30911w This report is exc}usively for the use of the client ir~dicated above and shall not be reproduced without written approval of HaC/Terracon