Old Townhomes-CS040211 T H E C I T Y 0 F~
COFFELL
P.O. Box9478
255 Parkway Blvd
Coppell, TX 75019
Phone:(972)304-3686
Fax:(972)304-7041
ENGINEERING DEPARTMENT
FAX CO VER SHEET
To: Kurt Jones From: Ken Griffin, P. E., Director of Engineering
Fax #: 972-735-9976 Date: 2/11/2004
Phone #: Pages: 5 (including cover sheet)
Re: Old Coppell Townhomes Fees CC:
( ) Urgent ( ) For Review ( ) Please Comment
( ) Please Reply
( x ) As Requested
Comments:
Preliminary fee assessment attached. Note that street light, street sign and construction
fees are not included until we receive additional information. Also, if the meter size
changes then the fee assessment will change. This fee assessmem only covers what is
referred to as Phase 1. Please provide a letter requesting that fees be assessed based on the
phasing.
Ken Griffin
IF YOU DO NOTRECEIVE ALL OF THE PAGES PLEASE CALL (972) 304-3686
"City of Coppell Engineering- Excellence By Design"
DEVELOPMENT FEE TABLE
Project: Old Coppell Townhomes (Preliminary Estimate)
Date: 2/11/2004
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $2,660.00
(100% due at Issuance o£ Building Permit)
Water Tap Inspection Fee $400.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic) S146.$6
(100% due at Issuance o£ Water Meter)
Water Meter Fcc (lrrigation/Fireline) $61.80
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic) $210.00
( 100% due at Issuance of Water Meter)
lrrigation/Fireline Meter Deposit $30.00
(100% due at Issuance of Water Meter)
Wastewater hnpact Fee $1,960.00
(100% due at Issuance of Building Permit)
Wastewater Tap Inspection Fee $350.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $350.00
(100% due at issuance of Building Pemait)
Park Fee $7,710.00 $7,710.00
(100% due prior to Council Approval)
Roadway Impact Fee $5,130.00 $5,130.00
(100% due prior to Council Approval)
Street Light Fee Information not Available
(100% due prior to Acceptance of Project)
Street Sign Fee Int'ormation not Available
(100% due prior to Acceptance oF Project) II
Construction Inspection Fee Information not Available
(100% due prior to Start of Construction) II
TOTAL $19,008.66
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $12,840.00
DEVELOPMENT FEE WORKSHEET
PROJECT: Old Coppell Townhomes (Preliminary Estimate)
DATE: 2/11/2004
Water impact Fee:
Domestic Meter(s):
Irrigation Meter(s):
Fireline Meter(s):
7 - 5/8 inch X 3/4 inch 7 ESU's
1 - 1 inch 2.5 ESU's
0 0 ESU's
0 0 ESU's
Total #: 9.5 ESU's @ $280.00 ea.
(Due prior to issuance of building permit)
Water Tap Inspection Fee:
Total #: 8 Connections @ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Domestic Water Meter Fee:
Total #: 7 Domestic Meter(s) @ $20.98
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Irrigation/Fireline Water Meter Fee:
Total #: 1 Irrigation Meter(s) @ $61.80
Total #: 0 Additional Irrigation Meter(s) @ $0.00
Total #: 0 Fireline Meter(s) @ $0.00
(100% due prior to issuance of water meters)
Domestic Water Meter Deposit Fee:
Total #: 7 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Irrigation/Fire Meter Deposit Fee:
Total #: 1 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU's: 7
(Due prior to issuance of building permit)
@ $280.00 ea.
Wastewater Tap Inspection Fee:
Total #: 7 Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total #: 7 Lots @ $50.00 ea.
(100% due prior to issuance of building permit)
$2,660.00
$400.00
$146.86
$61.80
$0.oo
$0.oo
$210.00
$30.0o
$1,960.00
$350.00
$350.00
Page1
DEVELOPMENT FEE WORKSHEET
Park Fee (For Residential Developments Only):
* Preliminary plat approved: After October 26, 1993
Park Development Zone:
6 Single-family @ $1,285.00 per lot
0 Multi-family @ $1,285.00 per unit
(100% paid prior to Council approval of final plat)
Zone 1
$7,710.00
$0,00
$5,130.00
Information not Available
Roadway Impact Fee:
(See attached fee calculations)
Street Lighting Fees:
Assessed for lighting in the City's right-of-way.
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
Street Sign Fees:
Assessed for signage in the City's right-of-way.
(See attached fee calculations if applicable)
Information not Available
Construction
Inspection Fees:
A copy of the development contract must be submitted for assessment,
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
Information not Available
Page 2
ROADWAY IMPACT FEE CALCULATIONS
PROJECT:
DATE:
Old Coppell Townhomes (Preliminary Estimate)
2/11/2004
ROADWAY IMPACT FEE:
Service Area * 5
,Category ** Residential
Land Use ** Residential Others Not Specified
X~o. Lots/Units 6
Development Units ** 6.00
Vehicle Miles per Development Unit ** 2.85
Fee per Vehicle Mile *** $300
Roadway Impact Fee due = (Development Units) x
(Vehicle M les per Development Unit) x (Fee per Vehicle Mile) = $5,130.00
* (Figure 2 - Road~vay Impact Fee Study)
** (Table 3 - Roadway Impact Fee Study)
*** (Schedule 2, Page 3 - Roadway Impact Fee Study)
HP Laser Jet 3330
City of Coppell
972 304 3570
Feb 11 2004 ll~28AM
F~Faax Call Report
Job Date Time Type Identification Duration Pages Result
316 2/il/2004 ]1:27:13AH Send 9727359976 1:17 5 OK