ST9602-CS040224 (2)PRE-CONSTRUCTION CONFERENCE AGENDA
MacArthur Boulevard Beltline Road
Date: February 24, 2004
Time: 10:00 A.M.
TxDOT Northwest Area Office
12000 Greenville Ave
Dallas, Texas 75243
Purpose of Meeting
At this conference, different organizations and departments will become
acquainted, establish lines of authority and communication and determine the
responsibilities and duties of the Contractor, TxDOT and other organizations
personnel.
II.
Introductions
A. TxDOT Employees
1. Interim Northwest Area Office Engineer: Praxedis Garza, P.E.
2. Area Office Design Engineer: Mauricc Pittrnan, P.E.
3. Project Manager: Duane Smith ln~,j~.dfOn/
4. Laboratory: Greg Price
5. Contract Administration: Brad Braden
III.
Prime Contractor: Gibson & Associates, Inc.
1. Project Superintendent:
2. Project Manager:
3. President:
4. Vice President:
Bill Kiker
Mark Person
James Long
Bill Gibson
JeffGibson
5. Executive Vice President: Tony Johnston
City of Coppell:
Dallas County:
Partnering
A. Introduction of the partnering concept.
B. Issue resolution & issue escalation.
TxDOT
Title Name
Project Manager
Area Engineer
Duane Smith
Praxedis Garza
C. Goals and expectations of each party.
IV. Review of Project
Gibson & Associates~ Inc.
Title Name
Project Identification
Control: 0918-45-321
Project: CM 96(907)
Highway: CS
Limits: MacArthur Boulevard at Beltline Road
County: Dallas
Type of Work:
Grading, Drainage Facilities, Traffic Signals, Asphaltic Concrete Pavement,
Signing and Pavement Markings.
Total Bid: $115~829.35
Work to be completed in 60 working days.
Working day definition is based on 5 calendar days charged per week.
Time charges will start:
D. Liquidated Damages- $ 400.00 per working day.
Discussion of Construction Plans
Item 8 of the Standard Specifications require the contractor to submit a critical path
method (CPM) schedule to outline the manner of prosecution of work he intends to
follow.
A. Prosecution and Progress
1. CPM Schedule: Preliminary schedule to be submitted.
2. Contractor expects to set barricades: ~
3. Contractor expects to begin construction: ~
4. Contractor expects to complete construction:
B. Traffic Control Plan
The Traffic Control Plan (TCP) included in the plans shows the minimum
requirements for construction signing and barricading during the course of this
project. Other additional signs and barricades may be required when and if
conditions warrant.
It is the Contractor's responsibility to both supply and maintain all necessary
traffic control devices. These devices must be standardized as to wording, size
construction, etc. as required by the Texas Manual of Uniform Traffic Control
Devices.
Should the Contractor wish to modify or utilize a different Traffic Control Plan
from that shown in the plans, it will be necessary to obtain approval from the State
prior to implementation. Request for modifications or changes must be in writing
along with any necessary drawings.
1.)
2.)
Major Highlights ~. ~' ~qlr~
Lane closures on ~ane shall not be allowed at the following
times
I.) 7 A.M. to 9 A.M. and 4:00 P.M. to 7 P.M. Monday thru Friday.
2.) Contractor will not be permitted to commence work on the road before
sunrise and shall arrange his work so that no machinery or equipment
shall be closer than 30 feet to the traveled roadway after sunset except
authorized by the engineer. 4~ln,t-
3.)
The Contractor shall abide by all provisions relating to obtaining
street cut permits an informing the public contained in the City of
Coppell Department of Public Works and Transportation's pavement
cut and repair standards manual.
Flaggers
Because daggers are responsible for the safety of both the traveling public
and the Contractor's personnel, it is important that qualified persons are
selected as daggers. The Contractor's attention is directed to Pan VI of
the Texas Manual on Uniform Traffic Control Devices for information on
the selection of daggers and flagging procedures. All daggers must wear
an orange vest, shin or jacket.
3.) Inspection of Traffic Control Devices
At approximately two week intervals the State will conduct formal
inspection of the-Contract6-r's traffic control devices, with alternate
inspection being conducted during the hours of darkness. Informal
inspections may be performed at any time. Copies of the inspection
reports will be furnished to the Contractor and any deficiencies must be
corrected within 48 hours.
To assure proper coordination between the State and the Contractor
concerning the Traffic Control Plan and the various traffic control devices,
both the Department and the Contractor will appoint a person responsible
for ensuring that the traffic control devices are used according to the traffic
control plans and standards.
Department Responsible Person (DRP)
Name: Duane Smith
Phone: Office: (972) 490 7400
Mobile: (817) 822 0946
Contractor's Resl)onsible Person (CRP)
Name: I ;ll f.'tl'.t -
Phone: Office:
'qT'Z-¢¢7-11q*f
Mobile:
VI. Equal Employment Opportunity Program
During the performance of any Federal-Aid contract, it is the intent of the Department to
determine that the Contractor conducts all aspects of his employment practices without
discrimination as to race, color, religion, sex or national origin. Further, it shall be
determined if the contractor has implemented an acceptable Equal Employment
Oppommity Affirmative Action Program.
A. Contractor's EEO Officer:
The Contractor must designate an EEO Officer for the project. This person must be
capable because of position in the company, authority and experience of promoting
an active and effective EEO program.
B. Contractor's EEO Meetings
Prior to the beginning of work, the contractor must conduct an EEO Policy Meeting
to explain and/or review the Company Policy and its implementation with all
supervisory and personnel office employees who will be directly connected with the
project. The Contractor is required to conduct these meetings at intervals not to
exceed six months during the period of construction.
C. Optional Training Special Provision:
The Contractor shall submit for approval the number of trainees to be trained in each
selected classification. The Contractor shall also specify the starting time for training
in each of the classifications and what training program will be used.
D. Bulletin Board
The bulletin board must be set up in a place where it is visible to all prime and
subcontractor employees. All EEO Officers names and policies for the prime and
subs must be posted on the bulletin board. Correspondence of EEO meeting will no
longer be sent to the main office. Instead, TxDOT inspectors may interview laborers
regarding EEO meetings.
E. It is brought to the Contractor's attention that Special Provision, Form FHWA-1273,
required contract provision for federal-aid construction, is attached to this contract.
VH. DBE Requirements
A. The goal for minority participation in each trade: 18.2 %
The goal for female participation in each trade: 6.9 %
The Contractor shall take all necessary and responsible steps to meet the goals for
this contract. The Contractor's performance in meeting his approved goal will be
monitored by the State.
B. DBE Subcontractor Approval
All DBE subcontractor approval forms must be submitted prior to starting work.
Also, all non-primary companies working on the job must be approved as a
subcontractor (including haul companies). Please reference commercial and non-
commercial tracking payroll guidelines. A copy of the signed agreement that
specifies exactly the work to be performed by the subcontractor must be submitted to
TxDOT.
C. Monthly DBE progress report
The Contractor's attention is directed to the applicable Special Provisions for a full
explanation of his obligations and responsibilities under this contract. DBE Monthly
Progress Reports will be required by the 15th of each month. TxDOT can furnish the
forms or the Contractors own form may be submitted.
D. DBE approvals
The Business Opportunities Program Office (BOP) must approve all DBE requests
prior to the DBE's performing work on the project. BOP Office approval is also
required for any DBE changes made throughout the duration of the project.
DBE goal credit will not be granted until approval from the BOP Office has been
obtained. All work performed prior to BOP Office approval will result in loss of
DBE goal credit for that work.
E. It is brought to the Contractor's attention that Form SMS 4902 - DBE prime
Contractor Payment to Non-DBE Subcontractors - must be submitted monthly.
VIII. Labor Laws
The Contractor shall submit a letter designating the Payroll Supervisor for this project.
The Contractor shall submit a copy of all subcontracts. The contractor and any approved
subcontractors shall submit copies of their weekly payrolls. The payrolls should be
submitted within two weeks to the Engineer.
**Late Payrolls may result in estimates being withheld.**
A. Work performed by laborers must match that of the payroll classification.
B. Designated payroll supervisor:
IX. Safety and Health
It is the State's responsibility to monitor the contractor for conformance to the various laws
concerning safety and health. However, it is the contractual obligation of the contractor to
comply with the State and Federal construction safety standards. Further, it is the
Contractor's responsibility for seeing that subcontractors comply with safety standards.
To document the Contractor's accident program the Contractor must answer the following
questions:
1. Does the Contractor have a definite safety program?
2. Does the program have the active and continued support of the company
management?
3. Has responsibility for safety been assigne.d, to a sl~ecific company official?
Safety Coordinator Name: '~,~1t 6~bb~t'v]
4. Does the Contractor make frequent safety inspections of operations of the project?
5. Does the Contractor discuss with his employees how to recognize and avoid unsafe
conditions and practices related to their individual work assignments?
Are periodic safety meetings held with employees?
Frequency of Meetings: ~e,e,~l~ ~
6. Are all occupational injuries and illnesses investigated by the Contractor, recorded
and reported?
Does the Contractor keep informed on governmental safety regulations and
standards?
XI. Utility Adjustments
The Contractor is responsible for damage to underground utilities located within the right
of way regardless of the inclusion or exclusion of their locations on the plans.
XII. General
B. Contractor Estimates:
1. Pay period (Cut-off) ends three working days before the end of the month.
2. Payment for material on hand: Before payment can be submitted a test report is
required and all material must be in approved storage. Material on hand requests must be
submitted on Forms 1914 and 1915 prior to the cut-off date.
C. All subcontractors request forms shall be submitted by the Contractor and approvals
granted by the Engineer prior to subcontractors beginning work on the project.
XIII. Required Information from Contractor
2. Safety Ofticer and Safety Program
3. EEO 'rogram Officer
4. Payroll Ofnoer
5. Contractor's Responsible Person (CRP) for Traffic Control and Emergency Numbers
6. Material Sources
7. Request for Subcontractor Approvals
8. Form CSTM-NRM-1 (Use of recycled materials)
9. Concrete Mix Designs
10. Asphalt Designs
11. Construction Schedule
XIV. Questions/Concerns:
XV. Adjournment