March 1, 2004
Darryl Miller
Pacific Builders
3360 Wiley Post Rd, Ste 100
Carrollton TX 75006
Fax972/866-9090
Mercantile Addition, Phase 1
Final Acceptance Conditions
Dear Mr. Miller:
On February 17, 2004 a walk-through inspection was conducted for the referenced project.
It appears that all punchlist items have been completed. At this time, the remaining
requirements for sign-offon the CO must be supplied. They are as follow:
1. Provide a maintenance bond from a registered surety for 50% of the contract value of
work performed in the public right-of-way and easements for a 2-year period beginning
on the date of final acceptance.
2. Provide record drawings of the public improvements from the engineer to be submitted
to City of Coppell Engineering Dept. (See attachment).
Once these items have been received, reviewed and accepted, I will sign offon the CO and
send a final acceptance letter. If you have any questions, please call me at 972/304-3679.
Sinc. oere~, !
Rick O Dell
Construction Inspector
Office Phone: 972/304-7090
Fax: 972/304-3570
CC;
Kenneth M. Griffin, P.E., Director of Engineering & Public Works
Glenn Hollowell, Assistant Director of Public Works
Greg Jones, Chief Building Official
Vernon Gilmore, Acting Fire Marshal
Attachment