August 18, 1995
Mr. Roy Hynds
M.A. Vinson Construction Co. Inc.
P.O. Box 185577
Fort Worth, Texas 76181
RE: Stream G-6 Drainage Project # DR 9346
Dear Roy,
Enclosed is your executed copy of the Change of Work Order # 2 on the referenced project.
This change addresses the relocation of all 8 inch water line located behind the north cllrb of
Bethel Road and includes all labor, material, equipment, etc. necessary to safely accomplish the
work.
If you have any questions, please call at your earliest convenience.
Thank you,
Construction Inspector
PROJECT:
CONTRACTOR:
OWNER:
CHANGE ORDER NO.: 2 DATE:
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
Stream G-6 Drainage Project # DR 93-06
M.A. Vinson Construction Co., Inc.
City of Coppell
August 14, 1995
ADD 1
DELETE
CHANGE OR EXTRA WORK TO BE DONE
Item Description Quantity Unit
#
Relocation of 8" W/L 1 L.S.
described in proposal
dated 8/10/95
N/A
Total Revision to Contract Amount
Unit
Price
19,775.00
Total
19,775.00
$19,775.00
Previous contract amount
Net increase in contract amount
Revised contract amount
Net increase in contract time of completion
Revised Contract time of completion
$ 230,208.08
$19,775.00
$249,983.08
20 CD
195 CD
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and furore liability originating under any clause in the Comract
by reason of this revision to the Contract.
Recommended b~the City Engineer:
Agreed to by tl~e Contractor:
Date:
Date:
Owner:
Date: