ST8402-CS 850108GINN, INC.
5anuary 8, 1985
CONSULTING ENGINEERS
C. R. SHAW & SON CONSTRUCTION CO.
P.O. Box 15127
Fort Worth, TX 76119
Attn: Paul Holliday
Re: Denton Tap Waterline Project
Change Order No. 1
Dear Mr. Holliday:
You are hereby authorized to proceed with the work as outlined by Change
Order No. 1 for an amount of $24,535.00.
The original contract time for this project was 120 calendar days which
expires on February 28, 1985. A 30 calendar day extension of time is
granted for the additional work, thus requiring all work on this project
to be completed by March 30, 1985.
If you have any questions, please do not hesitate to call.
Sincerely,
GI~, INC.
H. Wayne ginn, P.E.
City Engineer
KP:HWG:sr
cc: Ron Ragland, City Manager