ST8402-CS 850108GINN, INC. 5anuary 8, 1985 CONSULTING ENGINEERS C. R. SHAW & SON CONSTRUCTION CO. P.O. Box 15127 Fort Worth, TX 76119 Attn: Paul Holliday Re: Denton Tap Waterline Project Change Order No. 1 Dear Mr. Holliday: You are hereby authorized to proceed with the work as outlined by Change Order No. 1 for an amount of $24,535.00. The original contract time for this project was 120 calendar days which expires on February 28, 1985. A 30 calendar day extension of time is granted for the additional work, thus requiring all work on this project to be completed by March 30, 1985. If you have any questions, please do not hesitate to call. Sincerely, GI~, INC. H. Wayne ginn, P.E. City Engineer KP:HWG:sr cc: Ron Ragland, City Manager 1613q i'reqtm R,,~.~ · <". ~'6' ' Da21a,.Tcxa, 7'524~ · Pht.n~ 2!4 186-6611