WA0101-CS040426April 26, 2004
FWRM Inc.
P.O. Box 6173
San Antonio, Texas 78209-0173
T H £ C I T Y 0 F
COPpELL
RE:
S.H 121 Water Line / WA 01-01
Permanent Water Line Easement
Temporary Construction Easement
Dear Sir:
The City of Coppell is currently working with the engineering firm of Birkhoff, Hendncks &
Conway, L.L.P., to design the S.H 121 Water Line Project. Line 'A' begins at the intersection of
S.H. 121 and N. Coppell Road and runs northwest, generally within the southern right-of-way of
S.H. 121, to Denton Tap Road. Line 'B' comes off of Line 'A' and crosses under the futura S.H.
121 Bypass and ties into thc cxisting 8-inch water line located in thc utility easement between
Block C, Lot 79 and Block A Lot 51 of the Coppell Greens Phase Two Addition. The project is
in the final design phase and the City is in thc proccss of acquiring the land rights necessary to
construct the project. There are three permanent water line easements and three temporary
construction easements to be acquired within thc project limits. It will be necessary to acquire a
20-foot permanent water line easement and 50-foot temporary construction easement on property
that is owned by FWRM, Inc. Thc temporary construction easement is not filed with Dallas
County, so there will not be a permanent encumbrance on your property associatcd with this
easement.
With this letter I am providing a copy of the permanent watcr line casement and temporary
construction easement documents necessary for the construction of thc S.H. 121 Water Line
Project. Please review the enclosed documents and let me know if you have any questions or if
you wish to view thc construction plans. It is anticipated that construction will begin in October
2004.
Your consideration of this matter is appreciated.
Sincerely,
Suzalfhylor
CIP Oor~dinator
Engineering Department
Telephone: 972-304-7019
Fax: 972-304-3570
Enclosures
255 PARKWAY ~ PO BOX 9478 ~r CO?PELL 7× 75019 ~ ~ EL §?2/462 C3022 ~r FAX 972/304 3673
April26,2004
COPPELL GREENS LTD
4024 Naples Drive
Piano, Texas 75093-7040
T H IE C I T Y 0 F
COFFELL
RE:
S.H. 121 Water Line / WA 01- 01
Permanent Water Line Easement
Temporary Construction Easement
Dear Sir:
The City of Coppell is currently working with the engineering firm of Birkhoff, Hendricks &
Conway, L.L.P., to design the SH. 121 Water Line Project. Line 'A' begins at the intersection of
S.H. 121 and N Coppell Road and runs northeast, generally within the southern right-of-way of
S.H. 121, to Denton Tap Road Line 'B' comes off of Line 'A' and crosses under the future SH
121 Bypass and ties into the existing 8-inch water line located in the utility easement between
Block C, Lot 79 and Block A Lot 51 of the Coppell Greens Phase Two Addition. The project is
in the final design phase and the City is in the process of acquiring the land rights necessary to
construct the project. There arc three permanent water line easements and three temporary
construction easements to be acquired within the project limits. It will be necessary to acquire a
20-foot permanent water line easement and 35-foot temporary construction easement on property
that is owned by Coppell Greens Ltd. The temporary construction casement is not filed with
Dallas County, so there will not be a permanent encumbrance on your property associated with
this easement.
With this letter I mn providing a copy of the permanent water line easement and temporary
construction easement documents necessary for the construction of the S.H. 121 Water Line
Project. Please review the enclosed documents and let mc know if you havc any questions or if
you wish to view the construction plans. It is anticipated that construction will begin in October
2004.
Your consideration of this matter is appreciated
Sincerely,
Snza4 ylor
CIP C~/rdinator
Engineering Department
Telephone: 972-304-7019
Fax: 972-304-3570
Enclosures