Loading...
ST9302-CS 961115Sandy Lake Road: PROJECT STATUS November 15, 1996 Design Preliminary Plans: accepted by City Final Plans: 90% complete; meet w/consultant 12/96 to review Right-of-way: 35 parcels to acquire · Letters sent to 12 owners; have met w/four owners · Anticipate right-of-way to be complete mid-97 (this should allow time for any necessary eminent domain acquisition) Construction: · Utility relocation to begin in mid-97 (earlier if all right-of-way obtained) · Actual construction to begin in fall 97 (Contingent upon being able to work through the NCTCOG on obtaining the CMAQ funding for the Moore Road/Sandy Lake Road intersection in FY/1997. If that is not possible, the project will begin in early-1998.) Issues: Lower 30" water line to Town of Flower Mound Meeting held w/Dallas, Flower Mound, Lewisville, Upper Trinity River · Flower Mound to have alternate water supply in early-97 from Upper Trinity River to allow the existing 30" to be lowered with the Sandy Lake project Congestion Mitigation and Air Quality (CMAQ) funding for Moore/Sandy Lake (about SS00,000) Intersection has to be designed and approved by TxDOT Contract awarded to Unzicker, Schnurbush & Assoc. and the intersection removed from our contract w/Rady Right-of-way cannot be acquired until after Environment Impact Study (EIS) complete Intersection may need to be bid/built separately from the Sandy Lake project Cannot start intersection until after lowering of 30" water line Trying to work with TxDOT to allow inclusion in Sandy Lake $300,000 is allotted in FY 1998 by NCTCOG if project ready prior to that time, will petition NCTCOG to reallot funds to FY 1997 Summary: · Best Case: begin construction mid-97 · Realistic: considering CMAQ funding, EIS, right-of-way, begin construction early-98 SUBMITTED BY: 147 Director of Public Works/City Engineer