SS9901-CS040301 SUMMARY OF BIDS
FORCE MAIN LINES AAND B
DEFOREST ROAD LIFT STATION IMPROVEMENTS
CITY OF COPPELL
Bidder Bid Amount
Altemative I - HDPE by Directional Drilling
Hall Albert $1,487,892
Mastec $1,569,170
Barson $1,727,111
Insituform $1,920,702
Average $1,676,219
Minimum $1,487,892
Maximum $1,920,702
Median $1,648,141
Eng. Est. - Oct 03
Eng. Est. - Jan 04
$1,601,380
$1,381,800
Alternative II - Ductile Iron by Open Cut
Atkins Bros. $1,157,799
SJ Lewis $1,177,506
Bar $1,507,376
Barson $1,974,722
Average $1,454,351
Minimum $1,157,799
Maximum $1,974,722
Me_.~en $1,342,441
Eng. Est. - Oct 03
Eng. Est. - Jan 04
$1,433,053
$1,018,500
Contract Duration
No. Pits -A
No. Pits - B
210 days 6 2
250 days 10 3
120 days 7 2
270 days 8 2
Hall Albert
Insituform
150 days Bid R~ected
200 days
240 days
180 days
Atkins Bros.
Barson
Turner Collie ._ Braden Inc..
ENGINEERS.PLANNERS.PROJECT MANAGERS
17300 Dallas Parkway
Suite 1010
Dallas, Texas 75248
972-735-3000
Fax 972-735-3001
TRANSMITTAL
To: Mr. Kenneth M. Griffin, P.E.
Director of Engineering & Public Works
City of Coppell
255 Parkway Boulevard
Coppell, Texas 75019
Date: March 1, 2004
Re: DeForest Road Lif~ Station Improvements
Fome Main Lines A & B and Fome Main LineD
Job No.: 052131124.0001
Transmitted By: Courier
We are sending you the following:
Copies
1
1
1
1
1
1
Description
Force Main Lines A & B Bid Summary
Force Main Line D Bid Summary
Hall Albert Bid Qualifications (Lines A&B - HDPE)
S.J. Lewis Bid Qualifications (Line A&B - DI)
Mastec Bid Qualifications (Line D - HDPE)
Atkins Brothers Bid Qualifications (Line D - DI)
Remarks:
Please find enclosed the above referenced information. I have included the bid summaries for the
project and the qualification information received from each of the four low bidders. We are
currently verifying the information and checking references.
Copies To: File
Ted B. Sugg,
Project Manager