SS9901-CS040301 SUMMARY OF BIDS
FORCE MAIN LINE D
DEFOREST ROAD LIFT STATION IMPROVEMENTS
CITY OF COPPELL
Bidder Bid Amount
Alternative I - HDPE by Directional Drilling
Mastec $2,341,671
John Bums $2,951,760
Insituform $2,985,070
Barson $3,188,105
Hall Albert $3,193,570
Average $2,932,035
Minimum $2,341,671
Maximum $3,193,570
Median $2,985,070
Contract Duration No. Pits
300 days 11
180 days 8
300 days 10
150 days 9
270 da~s 10
Mastec
Hall Albert
'14 small pits
Eng. Est. - Oct 03
Eng. Est. - Jan 04
$2,798,540
$2,337,200
Alternative II - Ductile Iron by Open Cut
Atkins B~os. $2,593,996 180 days
Jackson $2,612,520 250 days
8J Lewis $2,661,044 300 days
Bar $2,851,168 300 days
John Bums $2,927,563 180 days
Barsen $3,336,913 210 da~s
Average $2,830,534
Minimum $2,593,996
Maximum $3,336,913
Med~ $2,756,106
Atkins Bros.
Barson
Eng. Est. - Oct 03 $2,836,240
Eng. Est. - Jan 04 $2,225,200
'lia r Collie ._ n Inc.
ENGI~EERSopLANNERS.PROJECT MANAGERS
17300 Dallas Parkway
Suite 1010
Dallaz, Texas 75248
972-735-3000
Fax 972-735-3001
TRANSMITTAL
To: Mr. Kenneth M. Griffin, P.E.
Director of Engineering & Public Works
City of Coppell
255 Parkway Boulevard
Coppell, Texas 75019
Date: March 1, 2004
Re: DeForest Road Lffi Station Improvements
Force Main Lines A & B and Force Main Lined
Job No.: 052131124.0001
Transmitted By: Courier
We are sending you the following:
Copies
1
1
1
1
1
1
Description
Force Main Lines A & B Bid Summary
Force Main Line D Bid Summary
Hall Albert Bid Qualifications (Lines A&B - HDPE)
S.J. Lewis Bid Qualifications (Line A&B - DI)
Mastec Bid Qualifications (Line D - HDPE)
Atkins Brothers Bid Qualifications (Line D - DI)
Remark:
Please find enclosed the above referenced information. I have included the bid summaries for the
project and the qualification information ~ceived from each of the four low bidders. We are
currently verifying the information and checking references.
Copies To: File
Ted
Project Manager