ST9801-CS000113 (2)FAX (214) 352-3201 TELEPHONE (214) 358-6581
ED BELL CONSTRUCTION COMPANY
POST OFFICE BOX 540787 10605 HARRY HINES
DALLAS. TEXAS 75354-0787 DALLAS. TEXAS 75220
January 13, 2000
Mr. Kevin C. Young, E.I.T.
Freese and Nichols, Inc.
1701 N. Market, Suite 500, LB 51
Dallas, Texas 75201
Coppell Road Reconstruction
SH 121 to Sandy Lake Road
Dear Mr. Young:
In accordance with your request for a revised cost break dom regarding the additional cost required to construct the
mulfple box culvert in two stages, the following information is provided for your review:
Stage 1
Dirtwork for one lane detour
Culvert for detour
HMAC for detour surface (161 TNS)
Remove detour
Striping for detours
Extra handling of dirt (2600 CY)
$10,000.00
$1,000.00
$12,700.00
$5,000.00
$1,000.00
$25,000.00
Stage 2
Dirtwork for demur
Provide and set CTB w/end protection (300 LF)
Remove CTB w/end protection
HMAC for detour surface (108 TNS)
Remove detour
Striping fqr detours
Labor/Equipment increase for decreased production
$6,000.00
$10,800.00
$3,500.00
$8,400.00
$3,000.00
$I,000.00
$52~000.00
Total $139,400.00
If you have any questions regarding this information, don't hesitate to contact our 6ffice.
crely,
tru3~nC°mpany
· Were;
Project Engineer
xc:
Mr. Kent Collins, P.E., Engineering and Public Works, City of Coppell
255 Parkway Blvd., Coppell, Texas 75019-4409
AN EQUAL OPPORTUNITY EMPLOYER