St Joseph-CS020225 ~ neoass~q
~ e~ement modiflcaltons and file the plaL Final
review and approval of Plat by city should take I week to 10
days. Mike's only concern on completing Plat is finalizing
easements with TXU. Filing the Plat with the county after the
City has approved is a requirement prior to the city's review
of building permit plans.
002.00 Mike Early Site 02/25/2 03/01/2
7 Millica Grading 002 002
n Permit
Mike Millican to submit final site grading plan and SWPPP
erosion control plan to the city along with a current copy of
all site utilities cleady marked as preliminary for reference
only. The city will review and agree to issue an eady site
grading plan with completion of the eady grading permit
application and submission of other required documents and
fees. (See checklist for eady grading permit)
~' 002,00 Mik~ Final 02/25/2 03/06/2
· 8 Millica Utility 002 002
n Plan
Final Utility Plans to be submitted to the city by 3/6/02 for
review.
002.00 Anthony Water 02/25/2
9 Meters 002
City will order water meters upon order and payment. City's
contract with Mfr. requires delivery within 45 days, currently
been receiving within about 2 weeks. City will not provide
meter to contractor until impact fees have been paid by
developer. Centex will order meters upon final submission of
utility drawings.
002.01 Mike
0 Millica
n
Fire Lane 02~25~2 03/06/2
Paving 002 002
The City needs a letter to provide a thickened (7") concrete
Fire Lane Paving section without lime stabilization in lieu of
lime stablized subgrade on private roadway. Star Leaf Road
and approaches from property line to Star Leaf Road will
require lime stablization. Mike to provide letter.
002.01 Anthony Temporary 02/25/2
1 Fire Lane 002
Utility (DWI J) to get the~ater valve-seeing the tank removed
and blind-flanged at DWU's main line adjacent to the site,
DWU has started excavation and a power pole has started
slipping into the excavation. DWU is to hand carry a check to
TXU or the new appropriate entity on Wednesday of this week in
order to have the power pole relocated. Previous indication
has been two weeks to schedule power relocation. Status of
schedule is currently unknown. Glenn will continue with
follow-up to have this work completed ASAP.
002.00 Anthony
~4
Tank Fill 02~25~2
002
Glenn Hollowell noted that the water in the tank is ground
water that the piping had been disconnected from the tank and
that the City could pump the tank out when demolition is to
begin. Centex may need to place a pump in the test port
manhole to the west to keep the tank dry dudng fill
operation. The city had previously used this to reduce ground
water around tank. Centex is to demolish the top of the tank
and sides down to existing grade, and the control building.
All demolition shall be pulverized to approx. 6" rubble at the
bottom of the tank. Additionally, a one foot section of the
tank will be broken from top to bottom to avoid trapping
water. Centex to provide 1Sack cement/sand mix as fill around
and over rubble to fill voids in rubble. Soil compaction above
cement/sand mix shall match requirements for compaction under
Star Leaf Road since roadway goes over the top of the old
tank.. Test Port Manhole shall be filled similiarly upon
completion of tank operation.
002.00 Ken 30" Force 02/25/2
5 Griffin Main Design 002
Ken noted that Turner Collie Braden were expecting to submit
final revised documents to him by March 1, 2002. He
anticipates only a day or two of review since the city has
previously reviewed the original layout and then will stamp
and release these documents for matedal order The piping is
designed as epoxy lined ductile iron and is specified on the
drawings. Centex anticipates a 3-4 week delivery from release
of material order and will request a preconstruction meeting
just prior to starting this work, under the same permit as the
Tank Demolition.
002.00 Mike Revisions 02/25/2 03/01/2
6 Millica to 30" 002 002
n Force Main
Easement
Due to revisions in layout of 30" Force Main the easement
along the west property line will need to be revised as an