SS9901-CN040710 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Deforest Road Lift Station Improvements Force Main Lines A & B CONTRACTOR: S.J. Louis Construction of Texas Ltd. OWNER: City of Coppell CHANGE ORDER NO.: Two (2) DATE: June 17, 2004 DELETE: ADD: Item Description Quanti~3' Unit Unit Price Total II-3 20" Ductile Iron Force 802 LF 340.00 ($272,680) Main by Bore w/36" II-7 30" Ductile Iron Force 88 LF 503.00 ($44,264) Main by Bore w/48" II-3a 20" Ductile Iron Force 472 LF 340.00 $160,480 Main by Bore w/36' II-3b 20"Ductile Iron Force 330 LF 325.00 $107,250 Main by Bore w/30" II-7a 30" Ductile Iron Force 88 LF 483.00 $42,504 Main by Bore w/42" Total Revision to Contract Amount ($6,710) Previous contract amount Net increase in contract amount/Change Ord. #1 Revised contract amount Net decrease in contract amount/Change Ord. #2 Revised contract amount Net increase in contract time of completion Revised Contract time of completion $1,177,506.00 $1,000.00 $I,178,506.00 ($6,710.00) $1,171,796.00 N/A N/A The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. ,~ted by City Date greed to ~I'~ ~D~e COFFELL July I, 2004 Sam Montoya, Project Manager S.J. Louis Construction of Texas 520 S. Sixth Street P.O. Box 834 Mansfield, TX 76063 Deforest Road Lift Station Improvements Force Main Lines A & B Project #SS 99-01 Change Order #2 Dear Mr. Montoya: Attached are three original Charge Order #2 documents for the referenced project. Please execute the documents and return two of the originals to me. One of the originals is for your file. If you have any questions please feel free to give Rick O'Dell, Construction Inspector, a call at 972/304-7090. Sincerely, Kenneth M. Griffin, P.E Director of Engineering3aublic Works Office 972/304-3686 Fax 972/304-7041 E-mail kgriffin~ci.coppell.tx.us C OPP-ELL P.O. Box 9478 255 Parkway Blvd Coppell, TX 75019 Phone: (972)304-3679 Fax: (972}304-7041 ENGINEERING DEPARTMENT FAX COVER SHEET To: Pete Stahl From: Ken Griffin Fax: 817-477-0552 Date: 6/17/04 Phone: Pages: 2 (including cover sheet) Re: CC: [] Urgent I~For Review [] Please Comment [] Please Reply [] As Requested .Comments: Attached for your review is Change Order #2 This is the way we will need to process the change order in order for it to work. The numbers vary some from yours. If it meets your approval let me know; and we will process the three originals for signatures and mail them to you. IF YOU DO NOT RECEIVE ALL OF THE PAGES PLEASE CALL (972) 304-3679 "City of Coppell Engineering- Excellence By Design" JUN-l?-2004 11:19 FROM S J LOUIS CONSTRUCTION TX TO 9721047041 P,01 TO: S,J. LOUIS CONSTRUCTION OF TEXAS LTO. LLP P,O. BOX 834 520 SOUTH 6TM AVENUE MANSFIELD. TEXAS 76063 OFFICE ~'1 ?-477-0320 FAX 817-477-0552 FROM: Pete Stahl, Senior Project Manager ~URGENT ~FOR REVIEW [] PLEASE COMMENT []PLEASE REPLY []PLEASERECYCLE JUN-l?-2004 11:19 FROM S J LOUIS CONSTRUCTION TX TO 9723047041 P.02 Request For Information (RFI) Coppell Deforest Road Lifi Station Improvements Force Main Lines A & B I-A 06/17/04 Mr. Ted B. Sugg, P.E. Peter J. Stahl. Tmner Collie & Braden Inc. Sen/or Project M Dallas, Texas 75248 Fax: {972) 735-3001 '- SJ. Louis Construction of Texas proposes one "no cost" change alternative on the above referenced project: · ConversionofthreelocationstohorlzontaldirectionMdrilting(HDD), Inordertomlnimizetraffic and surface disruption and increase the speed at which the project can be completed, our company requests three deep excavation areas be converted to HDD using HDPE (per project specifications): 1) STA 7+00 to STA 11+50 (450 LF), 2) STA 21+20 to STA 26+00 (480LF), and 3) STA 32+00 to STA 35+50 (250 LF). Again, this would be a "no co;t" change, as S.J. Louis Construction would have to compensate the driller for some areas which would previously had been installed by open cut methods, and open cut installation at shallow depth is much leas expensive than I'LDD methods. Payment would be made through pay estimate as if ductile iron pipe materials and casing had been installed without any changes. S.J. Louis Construction of Texas proposes one "credit to Owner" change alternative: · Downsizing of bored steel casing diameter. In order to reduce spoil material production and potentially use smaller boring equipment, which would reduce traffic and surface disrupt/on and increase the speed at which the project can be completed, our company requests 330 LF of 36" diameter steel casing be downsized to 30" in diameter for the 20" DIP (95 LF of 36" diameter ca~ing for 24" gravity SS PVC remains unchanged), and 88 LF of 48" diameter steel casing be downsized to 42" in &meter for the 30" DIP. The 30" diameter steel casing would still allow 4.7" of clear space from edge of pipe bell to inside wall of casing, while the 42" diameter steel casing would 11 allow 6.0 of clear space from edge sti ' of pipe bell to inside wall of casing. S.J. Louis Construction of Texas assumes all responsibility for ensur/ng that the pipe can be installed adequately inside the casing, and is completely confident there will be no problems. Credit to Owner: Total savings of 330 LF x $30.00/LF and 88 LF x $40.00/LF equals $13,420.00, to be split in half for value engineering with Owner receiving $6,710.00 credit, and S.J. Louis receiving $6,710.00 savings. Authorized $ignamr~ Les V. Whitman, S.J. Louis Construction of Texas Ltd., LLP File 14016 S.J. Louis Construction of Te~cas Ltd. P.O. Box g34 Mansfiel#, Texas 760~$ (81 7) 477-0520 Office (817) 477-0'~2 Fax TOTAL P.02