WA0101-MP040715SH 121 12-INCH WATER LINE WA 01~01 Birkhoff Hendricks & Conway 2005 Q1 Q2 ID Task Name DESIGN PHASE 2 Design 3 Project Meeting 4 95% Plans 5 Final Review Plans 6 Project Meeting 7 Project Meeting 8 Project Meeting 9 Advertisement 10 Bid Opening 11 City Council 12 PERMITS 13 TXDOT Permit 14 jTl[ I~Y CONFLICTS 15 Grande Communications (Advantex) 16 Brazos Electric Company 17 RIGHT-OF-WAY 18 Coppetl Greens Phase II Addition (WL/TCE) 19 Initial Contact by Cit7 20 Acquired by City 21 FWRM Inc, (WL/TCE) 22 Initial Contact by City 23 Acquired by City 24 SCl Denton Tap (Utility) 25 initial Contact by City 26 Acquired by City 27 CONSTRUCTION 28 Notice to Proceed 29 Construction (work days) 2002 2003 2004 . Q4 ~ ~ 02 Q3 i ~'~ Q1 Q2 03 . 9.4 i QI _ Q2 Q3 Q4 v · g/12 v v 7/1 · 10/21 · 3/g · 9/7 · 9/28 · 3/gv 4/26 · 3/9 · 4/14 · 10/18 Summary ~ Deadline Pmject:WA01-01 Task Milestone · Date: Thu 7/15/04 Page 1 SH 121 12-INCH WATER LINE WA 01-01 Birkhoff Hendricks & Conway 7 Project Meeting Will talk with TXDOT about moving outside of the 10-foot easement corridor for a portion of the water line, Will look at getting easements on the south end, 8 Project Meeting Met with doug Shower to discuss the new scale, the resolution of the utility conflicts and the easements. Difficulty in the FWRM property and the abstracts, 15 Grande Con~munications (Advantex) 06-07~4 - Potential conflict between the existing utility and the proposed 12-inch water line at three locations - may or may not require relocation, The total location length would be less than 200 feet. Engineer is meeting with TxDOT to determine their position on a vadable alignment in these locations which would minimize the need for relocation, if TxDOT is inflexible, enginer will prepare a request to Grande for a proposal to relocate. Utility will not commit money's to locate their line at the 4th location where the water line will cross the smell creek at Sra. 35+50. 16 Brazos Electric Company 07-02-04 - Transmission pole adjacent to station 15+20 - the pole foundation was designed to allow for an excavation of 5-foot depth adjacent to the pole. Engineer has prepared plan and profile to comply with these parameters. The plan sheet will include a note regarding the contractors responsibility to contact Brazos Electric at least 24 hours in advance of excavation local to this pole foundation. 21 FWRM Inc. 0NI. JTCE) 05-04-04 Jim Cummings, President of FWRM called and requested additional information 05-05-04 - Letter and information sent to Juim Cummings 06-30-04- offer letter sent to Jim Cummings 24 SCl Denton Tap (Utility) 05-28-04 - second letter sent P~e2