Hidden Valley-CS040716COl'FELL
Scott D. Caruthers, P.E.
Dowdey, Anderson & Associates
5225 Village Creek Dr., Suite 200
Plano TX 75093
July 16, 2004
RE: Hidden Valley Estates
Construction Plan Approval
Dear Mr. Caruthers:
The City of Coppell Engineering Department has reviewed the referenced plans and all of our
prior comments appear to have been satisfactorily addressed. For a permit to be issued on this
project, the City needs the following items submitted:
1. Payment for impact fees in the amount of $34,240.00 as per the Fee assessment letter of July
14, 2004.
2. A completed Construction Development Permit application (attached).
3. The appropriate number of plan sets for the City stamp and signature. We require three (3)
sets for our use, plus the additional number of sets you need stamped for your use and
contractor/subcontractor use. Contractors must have a stamped set of construction drawings
on the job site at all times.
4. Payment of construction inspection fees. Inspection fees are calculated at 2% of private
improvements and 4% of public right-of-way and easement improvements. Contracts or
contractor's estimate must be provided for verification. (Page three of the Construction
Development Permit is a spreadsheet for your convenience in calculating the fee.)
5. A copy of the executed NOI as filed with the TCEQ.
Once the above items have been submitted, a pre-construction conference will be scheduled ~vith
the assigned construction inspector. If you have any questions, please contact this office at your
convenience.
Sincerely,
Keith R. Marvin, P.E.
Civil Engineer
Phone: 972/0304-7044
Fax: 972/304-3750