Loading...
ST9301-CS040719Suzan Taylor - Re: E. Sandy Lake ST 93-01 Page 1 of 1 From: To: Date: Subject: "Don Snow" <don@seitexas.com> "Suzan Taylor" <staylor@ci.coppell.tx.us> 7/19/2004 3:01 PM Re: E. Sandy Lake ST 93-01 Suzan, Sorry for the delay in responding. We had staked the pole relocation on the north side of Sandy Lake where the drainage ditch will be and I sent the coordinates to Bill. I have talked with Bill about plotting these coordinates and then letting me know how far west I can move the pole to be approximately 5' back of new curb. As soon as I get this information, I can finish and submit design along with the permit form. We have to abide by a Public Utilities Commission ruling of filing a notification of transmission line relocations 45 days before commencement of work. This filing was done on July 15, therefore, work can not start until Sept 1. Don ..... Original Message ..... From: Suzan Taylor To: don (~,,seitexas.com Sent: Thursday, July 15, 2004 9:46 AM Subject: E. Sandy Lake ST 93-01 Don; Can you provide an update on the status of the two pole relocations along E, Sandy Lake? When do you anticipate submitting relocation plans for approval? Thanks Suzan 0 0 0 file://C :~Documents ¼20and ¼30Settings\staylor~Loca1¼20S ettings\Temp\GW} 00001 ,HTM 7/19/2004