Sandy Lake RoadBill,
Thank you for the information on proposed elevations.
Suzan,
You desire that the transmission poles be relocated before your construction begins. However, given that you will be placing
fill in the area where the poles will be placed, is there some way we could sequence the fill activity prior to moving the poles
so that the poles would not he in the way of the fill activity. This is especially so for the pole relocation on the north side of
Sandy Lake as 1 have no choice on the relocation but to move it west closer to the proposed curb. Please let me know your
thoughts on this.
Also, I want to let you know how much I appreciate Bill's help and input on detmaauning where we can place the new poles.
Thanks,
Don
..... Original Message .....
From: Pembroke, Bill
To: Don Snow
Cc: staylorQ)ci.coppell.tx.us
Sent: Tuesday, July 27, 2004 3:33 PM
Subject: Sandy Lake Road
Don:
Per your inquiry:
PP LOCATION EXIST. GROUND PROP. GROUND CONDITION
Sta 28+77, 48.22' RT 445.8 449.0 Relatively flat fill section
Sta 33+12, 40.00' LT 444.2 448.8 Relatively flat fill section
In both locations the PP will be placed in a relatively flat fill section. The elevations are approximate.
William G. Pembroke, P.E.
Senior Project Manager
Jacobs Civil Inc.
6688 N. Central Expressway
Suite 400, MB 13
Dallas, TX 75206-3924
ph: 214.424.7500
dir: 214.424.759I
fax: 214.696.3499
bill.pembroke@jacobs.corn
NOTICE - This communication may contain confidential and privileged
information that is for the sole use of the intended recipient. Any viewing,
copying or distribution of, or reliance on this message by unintended
recipients is strictly prohibited. If you have received this message in
error, please notify us immediately by replying to the message and deleting
file://C:\Documents%20and%20Settings\staylor\Local%20Settings\Temp\GW} 00001 .HTM 7/28/2004