RE: Sandy Lake Road, MacArthur Blvd. Construction
Gary:
Mr. Ken Griffin, City Engineer, requests the following information concern/ng the referenced
location:
What is your best guess as to when construct/on will start?
How many construction phases do you anticipate?
Which phase will be first?
How much time is anticipated for each phase and for the total construction?
And we need a traffic control plan.
This information is needed by Monday, December 4, 2000.