SS9901-CN040805 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: CONTRACTOR: OWNER: CHANGE ORDER Deforest Road Lift Station Improvements Force Main Line D MasTec North America, Inc. City of Coppell NO.: Two (2) DATE: 8/03/04 DELETE: Item Description Unit Owner Furnished Material: 30" MJ Horizontal Gate Valve 1 EA 22,750.00 30'x20" MJ Tee 1 EA 3,216.86 30" MJ 45© Bend 1 EA 2,589.48 20" MJ Plug 1 EA 350.10 30" Mega Lug 5 EA 644.5i 20" MJ Gland 1 EA 201.71 Total Revision to Contract Amount Quantity Unit Price Total 22,750.00 3,216.86 2,589.48 350.10 3,222.55 201.71 (32,330.70) Previous contract amount Net increase in contract amount Change Order #1 Revised contract amount Net decrease in contract amount Change Order #2 Revised contract amount Net increase in contract time of completion Revised Contract time of completion $2,364,835.54 $1,350.00 $2,366,185.54 ($32,330.70) $2,333,854.84 N/A N/A The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of ali past and future liability originating under any clause in the Contract by reason of this revision to the Contract. Acce~ !y Engineer Date y City /D~te DEFOREST ROAD LIFT STATION IMPROVEMENTS FORCE MAIN LINE D OWNER FURNISHED MATERIAL 30" MJ Horizontal Gate Valve 30" X 20" MJ Tee 30"MJ-45' Bend 20" MJ Plug 30" Mega Lug 20" MJ Gland I EA 22,750.00 22,750.00 I EA 3,216.86 3,216.86 1 EA 2,589.48 2,589.48 1 EA 350.10 350.10 5 EA 644.51 3,222.55 1 EA 201.71 201.71 TOTAL 32,330.70 · a sTe c August 5, 2004 Kenneth M. Griffin, P.E. Director of Engineering/Public Works City of Coppell 255 Parkway Blvd. Coppell, Texas 75019 Re: DeForest Rd. Lift Station Improvements Force Main Line D Project # SS-90-01 Change Order No. 2 Dear Mr. Griffin: Pursuant to your request we are enclosing herewith two executed copies of the referenced document. Please give us a call if we can be of assistance. Respectfully submitted, /M'a-~c North Ameg'ica David Holland Senior Vice President ...MasTec North America Inc 4747 Irving Bird Suite 221 Dallas Texas 75247 · 2145712500 fax 214 5712555 wwwmasteccom COl'FELL August 4, 2004 David Holland, Sr. Vice President MasTec North America, Inc. 4747 Irving Blvd., Suite 22l Dallas, TX 75247 FAX 214/571-2565 Deforest Road Lift Station Improvements Force Main Line "D" Project # SS 99-01 Change Order #2 Dear Mr. Holland: Attached are three original Charge Order #2 documents for the 'owner furnished materials' as has been discussed on the referenced project. Please execute the documents and return two of the originals to me. One of the originals is for your file. If you have any questions please feel free to give Rick O'Dell, Construction Inspector, a call at 972/304-7090. Sincerely, Kenneth M. Griffin, P.E. Director of Engineering/Public Works Office 972/304-3686 Fax 972/304-7041 E-mail kgfi ffin@ci.coppell.tx.us TIIN~-" 2FdD4 11:11 FR TIJRI'4ER COLLIES BRADEN'9,'72 ~==~ -,J 3882 TO 99723043578 p. EIi/CJ2 Turner Collie Braden Inc Engineers · Planncrs ·pro. h:ct Managers 17300 Dallas Parkway Suite 1010 Dallas, Texas 75248 972-735-3000 Fax: (972) 735-3001 DATE: TO: FROM: June 21,2004 # OF PAGES .includin¢ 2 Rick O' Dell George Cisneros FAX NUMBER: (972) 304-3570 PHONE NUMBER: (972) 735-3074 (If t[=nsmittal is Incomplete or unclear, please carl sender directly at this number.) REMARKS: As requested for Change Order #1, Owner Furnished Materials, following are prices and sources we were able to compile for the items listed in your fax dated June 17, 2004. Please let me know if we can be of further assistance Thanks, George Cisneros An AEOOM Company TOTAL PAGE.02 ~