COPPELL
~ August 6, 2004
Dear Mr. Jones:
I have seen no activity on the referenced project for some time. For that reason I am including a list of items
that must be addressed prior to the final walk-thru.
1. Grade the area around the outfall of the 33" storm drain.
2. Place rock riprap as per plans.
3. Remove spoils, broken limbs and stumps, construction debris and grade area over the outfall storm drain
system.
4. Clean storm drain system.
5. Backfill curb and shape parkway to final grade.
6. Clean streets.
7. Turn the interior fire hydrant to face the street.
8. Set meter cans.
9. Pour concrete pads around sanitary sewer service clean-outs and water valves.
10. Backfill west of Coppell Road.
11. Remove existing utility pole from entrance and pour concrete.
12. Provide a permanent solution to the ponding on the north side of the site.
13. Provide permanent erosion control protection.
14. Grade the barrow ditch along the east side of Coppell Road.
This is not a complete list of items that must be addressed prior to final acceptance. This list is provided to assist
you in preparing for the final walk-thru. If you have any questions, please contact me at (972) 304-3685 at your
earliest convenience.
Sincerely,
Garreth D. Campbell
Construction Inspector
# of
Post-it* Fax Note 7671 °ate~//O/~'~ Ipagesl' !
Ken Griffin, P.E., Director of Engineering & Public Works
Keith Marvin, P.E., Civil Engineer
Glenn Hollowell, P.E., Asst. Director of Public Works
Greg Jones, Chief Building Official
Tim Oates, Fire Marshal
T H E C I T Y O F
CO?PELL
Mr. Kurt Jones
Carbon Landmark, LLC
1701 N Collins Blvd, Ste 1200
Richardson TX 75080-3586
August 6, 2004
RE: Old Coppell Townhomes
Dear Mr. Jones:
I have seen no activity on the referenced project for some time. For that reason 1 am including a list of items
that must be addressed prior to the final walk-thru.
1. Grade the area around the outfall of the 33" storm drain.
2. Place rock riprap as per plans.
3. Remove spoils, broken limbs and stumps, construction debris and grade area over the outfall storm drain
system.
4. Clean storm drain system.
5. Backfill curb and shape parkway to final grade.
6. Clean streets.
7. Turn the interior fire hydrant to face the street.
8. Set meter cans.
9. Pour concrete pads around sanitary sewer service clean-outs and water valves.
10. Backfill west of Coppell Road.
11. Remove existing utility pole from entrance and pour concrete.
12. Provide a permanent solution to the ponding on the north side of the site.
13. Provide permanent erosion control protection.
14. Grade the barrow ditch along the east side of Coppell Road.
This is not a complete list of items that must be addressed prior to final acceptance. This list is provided to assist
you in preparing for the final walk-thru. If you have any questions, please contact me at (972) 304-3685 at your
earliest convenience.
Sincerely,
Garreth D. Campbell
Construction Inspector
CC:
Ken Griffin, P.E., Director of Engineering & Public Works
Keith Marvin, P.E., Civil Engineer
Glenn Hollowell, P.E., Asst. Director of Public Works
Greg Jones, Chief Building Official
Tim Oates, Fire Marshal