Loading...
ST9902-CS040830Suzan Taylor - RE: Sandy Lake Road (SH 121 to Coppell Road N.) From: To: Date: Subject: "Don McKelvain" <dmckelvain@brazoselectric.com> "Suzan Taylor" <staylor~ci.coppell.tx.us> 8/30/2004 3:41:16 PM RE: Sandy Lake Road (SH 121 to Coppell Road N.) Yes, I feel sure that we are talking about the same line. The tranmission circuit with TXU Electric Delivery is the only thing that Brazos owns along Sandy Lake Road. Don ..... Original Message ..... From: Suzan Taylor [mailto:staylor@ci.coppell.tx.us] Sent: Monday, August 30, 2004 2:39 PM To: Don McKelvain Subject: RE: Sandy Lake Road (SH 121 to Coppell Road N.) Don: I have been in touch with Richard Brewster. He has indicated that three concrete poles will have to be relocated near the TXU Electric Delivery substation, They are currently preparing the relocation plans. Do you know if these are the joint ownership utilities? Suzan Taylor >>> "Don McKelvain" <dmckelvain@brazoselectric.com> 8/30/2004 1:47:43 PM >>> Suzan: I've been out of town and I'm sorry it's taken me so long to respond. Brazos Electric has joint ownership of a double-circuit electric transmission line with TXU along the north side of Sandy Lake Road. I'm not sure at this time which company would be involved in designing and relocating the line. Have you been in contact with TXU about relocating these facilities? Don McKelvain Senior Right-of-Way Agent Brazos Electric Power Cooperative, Inc. 2404 LaSalle Ave. P.O. Box 2585 Waco, TX 76702 254-750-6339 ..... Original Message ..... From: Suzan Taylor [mailto:staylor@ci.coppell.tx.us] Sent: Wednesday, August 25, 2004 8:38 AM To: Don McKelvain Subject: Sandy Lake Road (SH 121 to Coppell Road N.) Don: The City of Coppell is working with the firm of Teague Nail & Perkins on the design of Sandy Lake Road, from SH 121 to Coppell Road N. The plans and specifications are 90% complete and the city is in the process of acquiring the right-of-way. The city is trying to determine a bid date for the project and would appreciate the following information related to your facility. .Suzan Taylor- RE: Sandy Lake Road (SH 121 to Coppell Road N.) ..... P__age 1. Does Brazos Electric have any facilities that will have to be relocated within the project limits? 2. Once the right-of-way is acquired and the utilities asked to relocate, how long will it take for Brazos Electric to prepare relocation plans and relocate the facilities? Your consideration of this matter is appreciated. Suzan Taylor CC: "Dave McDaniel" <dmcdaniel@brazoselectric.com>