ST9602-CS040622Ken Griffin - Page 1 i From: To: Date: 'Duane Smith" <dsmith3@dot.state.tx.us> <kgriffin@ci.coppell.tx.us> 6/22/2004 2:59:33 PM TxDOT is preparing to begin construction on the Beltline intersection as soon as the Contractors finish with the force main running through the existing median. Because of the rains and the existing utilities the projected date for them to be finished with our area is now next week. Our Contractor will begin construction after they are finished, They will be ready for the grade crossing to be installed in ten to fourteen working days after starting construction. This would have the railroad work on the weekend of 7/16/04 or the weekend of 7/23/04. Could you notify the City Council the construction is beginning and the rebuilding of the railroad crossing is coming soon. As soon as we have a good start date we will notify you of the exact detour dates. CC: <cgoodroad@dallascounty.org>