ST9905-CS040915Suzan Taylor - RE: Bethel Road Agreement
Page 1 of 2
From: "Patrick Nwakoby" <pnwakoby@expl.com>
To: "Suzan Taylor" <staylor~ci.coppell.b(.us>
Date: 9/15/2004 6:31 AH
Subject: RE: Bethel Road Agreement
Good morning Suzan!
No problem - let me know after you review if that is the only item you want to revise. Thanks for your help.
Patrick
.... [Patrick Nwakoby] -Original Message .....
From: Suzan Taylor [mailto:staylor@ci.coppell.tx.us]
~ent: Tuesday, September 14, 2004 4:39 PM
To: Patrick Nwakoby
Subject: RE: Bethel Road Agreement
Patrick:
I appreciate the quick response and we do not want to 'rock the boat' - would it be possible to change
Item No. 6 to read:
City shall not permit any machine excavation nor allow heavy equipment to work within 10 feet either
side of Explorer's 12-inch pipeline without Explorer's field representative being present.
If you do not want to change it - that is fine.
Thanks
>>> "Patrick Nwakoby" <pnwakoby@expl.com> 9/14/2004 4:25:57 PFI >>>
Good afternoon Suzan!
Thank you for your e-mail.
Item #6 is to prevent any equipment working near the pipeline without an Explorer Rep. on site. Your
contractor can work near the pipeline. We just want to ensure that Explorer is notified so that someone
from Explorer is present. Please let me know if this helps. Thanks.
Patrick
..... Original Message .....
From: Suzan Taylor [mailto:staylor@ci.coppell.tx.us]
~ent: Tuesday, September 14, 2004 4:08 PM
To: Patrick Nwakoby
Subject: Bethel Road Agreement
Patrick:
Patrick:
In reviewing the agreement - we have concerns about Item No. 6 that states:
City shall not permit any machine excavation nor allow heavy equipment to work within 10 feet
either side of Explorers 12-inch pipeline without prior approval of Explorer's field representive.
We are entering into this agreement because the city wants to construct roadway improvements
file://C :XDocuments%20and%20Settings\staylorkLocal%20Settings\Temp\GW} 00001 .HTM 9/15/2004
Page 2 of 2
that are within 5 feet of your 12-inch pipeline. The proposed back-of-curb is 5 feet away from the
pipeline at the closest point. We know in advance that we can not construct these roadway
improvements without having paving operation equipment within 10 feet either side of the
pipeline. The paving machine extends out three to four feet beyond the back of curb.
Could Item No. 6 be reworded to state:
City shall not permit any machine excavation nor allow heavy equipment, other than the paving
operation equipment, to work within 10 feet either side of Explorers 12-inch pipeline without prior
approval of Explorer's field representive.
Thanks