ST9905-CS041209T H E C I T ¥ 0 Ir
COl'FELL
December 9, 2004
Mr. Rez Samari
Verizon Communications
2094 McGee Lane
Lewisville, Texas 75077
RE: Bethel Road I
ST 99-05
Utility Relocations
Mr. Samari:
The Bethel Road I project consists of both roadway and channel improvements. The existing two-lane
asphalt road will be replaced with a four-lane divided roadway. Right-of-way acquisition for the roadway
portion, from the west city limits to east of Freeport Parkway is complete. A 95% complete set of plans
and a Right-of-Way Use Perrnit are enclosed. Verizon Communications submitted a permit for the utility
relocations on this project in June 2003. Please review the plans to ensure that your relocation plans are
still current and complete a new permit form for submittal to the city. Utility relocations can be initiated
upon approval of the pen:nit.
The channel improvements are generally outside of the roadway improvements. They begin east of
Freeport Parkway and south of Bethel Road and extend in a northeasterly direction. A new four-barrel
box culvert will be constructed across an unimproved section of Bethel Road as part of this project. The
city is working with the project consultant on the design of the channel and with the United States Corps
of Engineers on obtaining a permit for the construction. Plans will be forwarded to you once they are
complete. One parcel of right-of-way will need to be acquired for the channel construction.
This project Is scheduled to advertise in the 1't quarter of 2005. Should you have any questions or need
any additional information, please advise.
Sincerely,
Suz(n ~. Taylor
C1P[Go~rdinator
Engineering Department
Direct: 972-304-7019
Fax: 972-304-3570
E-mail: ~aD~lor ¢~_c op p e_ll .t x ._u~
Enclosures
T H £ C I T Y 0 F
COPPELL
December 9, 2004
Mr. Doug Brewer
Atmos Energy
200 N. Ector Drive
Euless, Texas 76039
RE: Bethel Road I
ST 99-05
Utility Relocations
Mr. Brewer:
The Bethel Road I project consists of both roadway and channel improvements. The existing two-lane
asphalt road will be replaced with a four-lane divided roadway. Right-of-way acquisition for the roadway
portion, from the west city limits to east of Freeport Parkway is complete. A 95% complete set of plans
and a Right-of-Way Use Permit are enclosed. Please review the plans to determine if Atmos Energy has
any facilities impacted by the proposed improvements. Utility relocations can be initiated upon approval
of the relocation plans and permit.
The channel improvements are generally outside of the roadway improvements. They begin east of
Freeport Parkway and south of Bethel Road and extend in a northeasterly direction. A new four-barrel
box culvert will be constructed across an unimproved section of Bethel Road as part of this project. The
city is working with the project consultant on the design of the channel and with the United States Corps
of Engineers on obtaining a permit for the construction. Plans will be forwarded to you once they are
complete. One parcel of right-of-way will need to be acquired for the channel construction.
This project is scheduled to advertise in the st
1 quarter of 2005. Should you have any questions or need
any additional information, please advise.
Sincerely,
ylor
ator
Engineering Department
Direct: 972-304-7019
Fax: 972-304-3570
E-mail: st aylg~(~a~c i.c opA~e Il. tx .us
Enclosures
COPPELL
December 9, 2004
Mr. Roger Cloninger
McLeod USA
15601 N. Dallas Parkway, Suite 700
Dallas, Texas 75001
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Cloninger:
The Bethel Road I project consists of both roadway and channel improvements. The existing two-lane
asphalt road will be replaced with a four-lane divided roadway. Right-of-way acquisition for the roadway
portion, from the west city limits to east of Freeport Parkway is complete. A 95% complete set of plans
and a Right-of-Way Use Permit are enclosed. Please review the plans and let me know, either way, if
McLeod USA has any facilities impacted by the proposed improvements. Utility relocations can be
initiated upon approval of the relocation plans and permit.
The channel improvements are generally outside of the roadway improvements. They begin east of
Freeport Parkway and south of Bethel Road and extend in a northeasterly direction. A new four-barrel
box culvert will be constructed across an unimproved section of Bethel Road as part of this project. The
city is working with the project consultant on the design of the channel and with the United States Corps
of Engineers on obtaining a permit for the construction. Plans will be forwarded to you once they are
complete. One parcel of right-of-way will need to be acquired for the channel construction.
This project is scheduled to advertise in the 1st quarter of 2005. Should you have any questions or need
any additional information, please advise.
Sincerely,
Suzan . Taylor
CIP Coordinator
Engineering Department
Direct: 972-304-7019
Fax: 972-304-3570
E-mail: stavlorCd~ci.coppelt.tx.us
Enclosures
COPPELL
December 9, 2004
Mr. Tim Norris
OnFiber Carrier Services
1820 N. Glenville Drive, Suite 114
Richardson, Texas 75081
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Norris:
The Bethel Road I project consists of both roadway and channel improvements. The existing two-lane
asphalt road ;vill be replaced with a four-lane divided roadway. Right-of-way acquisition for the roadway
portion, from the west city limits to east of Freeport Parkway is complete. A 95% complete set of plans
and a Right-of-Way Use Permit are enclosed. Please review the plans and let me know, either way, if
OnFiber Carrier Services has any facilities impacted by the proposed improvements. Utility relocations
can be initiated upon approval of the relocation plans and permit.
The channel improvements are generally outside of the roadway improvements. They begin east of
Freeport Parkway and south of Bethel Road and extend in a northeasterly direction. A new four-barrel
box culvert will be constructed across an unimproved section of Bethel Road as part of this project. The
city is working with the project consultant on the design of the channel and with the United States Corps
of Engineers on obtaining a permit for the construction. Plans will be forwarded to you once they are
complete. One parcel of right-of-way will need to be acquired for the channel construction.
This project is scheduled to advertise in the 1st quarter of 2005. Should you have any questions or need
any additional information, please advise.
Sincerely,
Taylor
dinator
Engineering Department
Direct: 972-304-7019
Fax: 972-304-3570
E-mail: staylor(a!ci.coj)pell.lx.u5
Enclosures
December 9, 2004
Mr. Richard Brewster
TXU Electric Delivery Company
301 S. Harwood Street, 6 South
Dallas, Texas 7520 l
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Brewster:
The Bethel Road I project consists of both roadway and channel improvements. The existing two-lane
asphalt road will Be replaced with a four-lane divided roadway. Right-of-way acquisition for the roadway
portion, from the west city limits to east of Freeport Parkway is complete. A 95% complete set of plans
and a Right-of-Way Use Permit are enclosed. Please review the plans to determine if TXU Electric
Delivery has any facilities impacted by the proposed improvements. Utility relocations can be initiated
upon approval of the relocation plans and permit.
The channel improvements are generally outside of the roadway improvements. They begin east of
Freeport Parkway and south of Bethel Road and extend in a northeasterly direction. A new four-barrel
box culvert will be constructed across an unimproved section of Bethel Road as part of this project. The
city is working with the project consultant on the design of the channel and with the United States Corps
of Engineers on obtaining a permit for the construction. Plans will be forwarded to you once they are
complete. One parcel of right-of-way will need to be acquired for the channel construction.
This project is scheduled to advertise in the 1st quarter of 2005. Should you have any questions or need
any additional information, please advise.
Sincerely,
Su aylor
CIP Cso~dinator
Engineering Department
Direct: 972-304-7019
Fax: 972-304-3570
E-mail: stavlor(a)ci co22petl.tx.us
Enclosures