May 17, 2000
Mr. Kenneth M. Griffin, P.E.
Director of Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019-4409
Re:
Sandy Lake Road Reconstruction
Coppell Project #: ST 93-02
Kimley-Hom Project #: 06940600
DWU Project #: 98-31IF
Dear Mr. Griffin:
Enclosed for your review is a revised schedule for the referenced project reflecting the current
state of the project and our proposed sequence of work to complete the project. It is our intent to
attempt to accelerate the phase 2 and phase 4 work in an effort to start the DWU lowerings
during this summer and be prepared to make the connections as soon as the DWU work window
opens. This schedule indicates that the project, less the MacArthur intersection, will be
completed in June 2001.
If you have any questions regarding this schedule, don't hesitate to contact our office.
Sincerely,
~C~s~n Company
Robert D. Weber
Project Engineer