St Andrews Est-CS041220COPPELL
December 20, 2004
Terry Holmes
Holmes Builders
2629 Dickerson
Carrollton TX 75007
RE: Construction of Barrier-Free Ramps
Dear Mr. Holmes:
We received your letter dated October 1, 2004 seeking to delay the construction of the four
proposed barrier-free ramps planned for this project. You asked for delay until the construction
of the homes for the subdivision takes place. The design submitted is correct, however please
adhere to the following conditions:
1. The City will allow construction of the two interior ramps to be delayed until the homes are
built on those two lots.
2. The ramps adjacent to Deforest Road must be constructed before final acceptance of the
infrastructure portion of the project. This activity should take place so that the maintenance
bond will be in effect for those facilities during the 2-year bond period.
3. When the ramps for Lots 18 and 19 are to be constructed, please call this office for inspection
services.
4. The ramps at the intersection of Stonewick Ln shall be constructed within the 2-year
maintenance period.
If you have any questions or comments, please contact me at your convenience.
Sincerely,
Keith R. Marvin, P.E.
Civil Engineer
Office: 972-304-7044
Fax: 972-304-3570
CCi
Larry Davis, Construction Inspector
Greg Jones, Chief Building Official
255 pARKWAY ~r p.O.BOX 9478 ~ CoPPeLL TX 75019 ~ TEL 972/462 0022 ~ FAX 972/304 3673