Project Number: CPL03243
TO:
FROM:
DATE:
RE:
CC:
Ken Griffin, P.E., Suzan Taylor
Tricia H. Hatley, P.E.
December 1,2004
Bethel Road II Construction
Sam Meisner, Scott Fisher, Bow Lin
Project Updates:
· Attached is a revised schedule showing the next submittal date and the overall
projec~ impact.
· We have received a few revised documents from the surveyor and will be sending
those on to Suzan in the next few days.
· Submitted plans for preliminary ADA/TAS review.
Tasks and deliverables for the next two weeks: · Submit revised ROW of documents.
· Project Meeting. Discuss hike/bike trail layout, 60% sewer comments, ADA/I'AS
review comments and construction sequencing.
· Submit 90% plans.
Date:
12/6/04
1/20/05, 2pm
1/31/05
Deliverable:
Updated ROW documents
Project Meeting
90% plan submittal