SS9901-CS050118Canfer Construction Company, Inc. Todd C. ltoff, Project Manager 11031 Grissom Lane Dallas, TX 75229 FAX 972/4844223 'IT Y - 0 COl'FELL January 1B, 2005 RE: Detbrest Road & Sandy Lake Wastewater Lift Stations Project # SS 99-01 Request for Time Extension Dear Mr. Hoff: This letter is written in response to your January 13, 2005 letter in which you requested an extension of fifty-one (51) days. That request cannot be acted upon because all required information has not been submitted. The contract (on page 3-6 of the Standard Specification Supplementary Conditions) states "No extension of the contract time shall be allowed unless the CONTRACTOR can demonstrate the delay caused an adverse impact to the critical path and that loss of time cannot be made-up by revising the sequence of the work of the project." Your letter references several items related strictly to relocation of utilities. However, the contract requires that you review your entire Project Schedule to ascertain whether or not the requested extension can be made-up by revising critical path items. Again, before the request can be acted upon you need to revise and resubmit a Project Schedule similar to the one you provided on November 15, 2004, ~vhich list ail project components and the estimated time. That ProJect Schedule should dearly denote the critical path items so that a decision can be provided. Also, please be advised that the Project Schedule you previously submitted shows that at least twenty-seven (27) days were being dedicated to powerline, cable and fiber optic relocations. So at a bare minimum, the only extension the City would consider would be an extension over and above the time already noted in your schedule allocated for those items. Again, that decision cannot be made until a revised schedule has been provided per the contract. The last sentence of your letter states that 27% of the requested days have been "weather days". Please be advised that no consideration is provided for "weather days" in a contact in which it is bid strictly as "calendar days". If you have any questions or need any additional information please feel free to contact this office. If not, the City will await the submittal ora revised Project Schedule showing critical path items befbre it acts upon your request. Smcerely, Kenneth M. Griffin, P.E. Director of Engineering/Public Works Office 972/304-3686 Fax 972/304-7041 E-mail k&q'i CCZ Rick O'Dell, Construction Inspector Erika Cooper, Turner, Collie & Bradcn/Fax 972-735-3001