Coppell Trade-CS050126T H [ ' C I T COFFELL January 26, 2005 Richard W. Akin, P.E Macatee Engineering 6440 N. Central Expressway, Suite 414 Dallas, TX 75206 RE: Coppell Trade Center/Lot 1, Block 1 Construction Plan Review Comments Dear Mr. Akin: The City of Coppell has reviewed the referenced plans and has the following comments to offer: Minor Plat 1, Provide the volume and page information for the existing 20' utility easement that will be partially abandoned. 2. Describe by metes and bounds the portion of the existing 20' utility easement to be abandoned by his plat. 3. The 24' firelane and access easements do not include public utilities. Utility easements are being platted separately, Remove "utilities" from the fire and access easements on this page and throughout the drawing set. Curves C23 and C24 do not meet fire lane requirements. Additionally, C24 is not listed in the Firelane Curve Data table. Provide a statement on the plat indicating that the maintenance of the drainage easement is to be by the owner. Provide a future ROW dedication reservation for Freeport Parkway at the northeastexm comer of the property. Modify the 20' utility easement described by UL1, UL2, UL3, UL4, UL5 and UL6. Place the 2" meters in a 20' x 20' (square) easement at the southeast comer of the property. Provide an additional note that states "Sidewalks will be constructed at the expense of the property owner when deemed necessary by the City Engineer." Move in the direction of finalizing the plat while preparing for re-submittal of the drawing set. Upon re-submittal, preliminary verbiage should be finalized. Refer to mark-ups. 5. 6. 7. 8. 9. Paving & Dimensional Control, Sheets 2 & 3 of 16 1. Tie down the existing TXU poles and show their locations on the drawings. Ensure they do not conflict with the drives. 2. Refer to the Subdivision Ordinance for minimum requirements of stamped concrete at the drives. 3. Modify the temporary asphalt-paving note to state "Construct asphalt paving connection from the property line to the existing road for temporary use." 4. Ensure that the proposed grades for the site will not conflict with the City's plans for future road improvements along Sandy Lake Road, specifically for drainage and pavement connections. 5. Construct the channel crossing with the first phase of development. 6. Remove "utility" from the 24' fire and access easement as described on the plat comments. 7. Construction Notes: 6. Pavement specifications in the notes shall match the specifications in the Pavement Legend. Refer to the Subdivision Ordinance and include specifications for hand pours and irregular sections. 7. City of Coppell standard is silicone joint sealant. 8. Refer to the Subdivision Ordinance for sub-grade preparation requirements. Include lime- stabilized sub-grade in the Fire Lane Paving detail and Pavement Legend specifications. 10. Lane closures may occur only between 9:00 a.m. and 3:30 p.m. General: Correct typographical errors. 8. Details: Demonstrate (show sections) the variable inverts at inlet locations. Additionally, include a Temporary Asphalt Paving Section detail. 9. Legend: Include Temporary Asphalt Paving and Stamped Concrete in the legend. Indicate these areas on the drawing. Mobilization and Rough Grading ~ Erosion Control, Sheet 4, 5 & 6 of 16 1. There is an existing well on the site. Show its location on the drawings. Contact the City of Coppell Department of Environmental Health to abandon the well per appropriate regulations. 2. Add a note to the drawing informing the contractor that adjacent properties house livestock. Perimeter fencing that needs to be moved for construction activities must be coordinated with the appropriate landowners to ensure livestock is not allowed to roam freely. Any accidental damage to the fencing must be repaired immediately to constrain the livestock. 3. The silt fencing shown on the drawing does not appear to be adequate for the amount of potential run-off from the site. Consider check dams or other methods to prevent erosion within the channel. 4-. Silt fence filter material shall be wire-backed. 5. Stabilized construction entrance shall use 3"-6" rock. Refer to mark-ups. 6. All erosion control measures shall be provided and installed in accordance with TCEQ and the City of Coppell Standard Construction Details. Phase I Grading Plan, Sheet 7 of 16 1. Provide more detail especially around grates and inlets, retaining wall, building footprint and "X's" marked on the sheet. Mass Grading Plan, Sheet 8 of 16 1. Provide finished floor elevations of future buildings. 2. How will the undeveloped site areas drain prior to the installation of the storm system? Refer to mark-ups. 3. Construct the culverts with the first phase of development. Refer to mark-ups. 4. Seed the entire site after the mass grading to prevent erosion. 5. A detailed review of future phases may impact this grading plan Channel Plan & Profile, Sheet 9 of 16 1. The City strongly suggests that any structures within the limits of the channel, including, but not limited to culverts, utility crossings, and future head walls be constructed with this phase to prevent stabilizing the channel more than once. 2. Is the rip-rap shown adequate to dissipate the flow from the channel? Add dissipaters at the end of the channelized flow (around section line B-B). 3. Show culverts in the profile view. Drainage Area Map, Sheet 10 of 16 1. Add Line "F" to the table of calculations. 2. Will culverts be placed in the drainage easement where the road crosses? Show them on the drawings. 3. Some of the discharge velocities appear high. Is the specified rip-rap adequate to dissipate these flows? Erosion problems will be at the expense of the owner. Storm Sewer Plan & Profile, Sheet 12 of 16 1. Show the water lines and sanitary sewer lines in the plan and profile views on this drawing. Verify there are no conflicts between the lines. 2. Change the North arrow to point in the correct direction. Storm Sewer Plan & Profile, Sheet 13 of 16 1. Show the water lines and sanitary sewer lines in the plan and profile views on this drawing. Verify there are no conflicts between the lines. 2. Will Class III RCP work with one foot of cover? 3. Consider moving the grate inlets further from the parking area and closer to the main pipe. 3. Change the North arrow to point in the correct direction. Water & Wastewater Plan, Sheet 14 of 16 1. Refer to wastewater or sanitary sewer. Use consistency in terminology throughout the drawing set. 2. Provide a detail of the abandonment of the existing sanitary sewer. 3. Fire hydrants shall be no more than 300' apart along the fire lane. 4. Show the storm sewer line on this drawing. Verify there are no conflicts between the lines 5. Place the 2-2" taps and meters in the 20' x 20' easement as described in the plat comruents. 6. Verify the existence of the 12" stub-out and valve. Provide a plan of the connection to it including the 247.10' of 8" pipe. 7. Private Utility Notes: 6. Water lines shall be C900 PVC, DR-14 Class 200. 12. SDR-35 PVC shall be green in color. Water & Wastewater Plan, Sheet 15 of 16 1. Provide a detail of the abandonment of the existing sanitary sewer. 2. Change the label of the "Proposed 8" SS" to "Construct Public 8" SS Line." 3. Remove the curvature from the 8" SS line or set a manhole at the point oftangency. 4. The contractor shall perform a TV examination of the existing 8" SS line after completion of all tree removal and connection of SS Line "S 1". Any damage shall be repaired or replaced to the City's satisfaction prior to paving. 5. The drawing calls out to connect to an existing 8" water stub-out. This is in fact a 12" stub- out, however it is not installed yet. If your development takes place prior to the development to the west, you may be required to construct this line to make your project work. 6. Construct all channel crossings with this phase. Plug on the other side of the channel. Refer to mark-ups. Wastewater Profile, Sheet 16 of 16 1. Follow TCEQ guidelines for separation and mitigation requirements for water lines. 2. Manholes deeper than 12' (but shallower than 20') shall be 5' diameter. Please make the necessary changes and submit these marked-up plans and two sets of revised plans to the City for review. If you have any questions, please contact this office at your convenience. Sincerely, Charlene La Matt~a, E.I.T. Graduate Engineer Office Phone: (972) 304-3681 Fax: (972) 304-7041