SS9901-CS050119Turner Collie (0'Braden Inc TRANSMITTAL
From:
Date:
Job No.:
Subject:
See Distribution ~c,¢~
Erika K. Cooper, P.E. - TCB
January 19, 2005
052 131124.0001 04000.A123 (2.1)
Deforest and Sandy Lake Wastewater Lift Stations and Force Main Improvements
DeForest & Sandy Lake Wastewater Lift Stations
Shop Drawing Review Comments
Submittal No. 04-44-017A Rev 1 (Raven Coating)
Submittal No. 04-44-024A (DeForest Lighting)
Submittal No. 04-44-025A (Sandy Lake Lighting)
Submittal No. 04-44-029A (Electrical Submittal)
Submittal No. 04-44-030A (Gate Valve)
Submittal No. 04-44-032A (Air Valve)
Submittal No. 04-44-033A (Check Valve)
TCB has the following comments on these submittals:
Description Status Comment
Raven Coating No Exception Taken
DeForest Lighting No Exception Taken
Sandy Lake Lighting Make Corrections Noted · Verify quantities
Electrical Submittal No Exception Taken
Gate Valve Make Corrections Noted · Provide three (3) 12-inch gate valves
per Plans. Verify all quantities.
· Provide spur gearing for valves 24" and
larger per Specification Section 15107.
· If gearing is required for 20" valves,
provide spur gearing.
Air Valve Make Corrections Noted · Provide air valves with reinforced nylon
bodies.
Check Valve No Exception Taken
When you re-submit the shop drawings, please address all comments and submit eight (8) copies to
this office.
Distribution:
[X] 2 copies of submittal to the City
[X] 4 copies of submittal to Can-Fer Construction Company, Inc.
[X] 2 copies of submittal to TCB file
[ ] Other