SS9901-CS041215Turner Collie Braden Inc. TRANSMITTAL
From:
Date:
Job No.:
Subject:
See Distribution~..p. ~'
Enka K. Cooper, P.E. - TCB
December 15, 2004
052 131124.0001 04000.A123 (2.1)
Deforest and Sandy Lake Wastewater Lift Stations and Force Main Improvements
DeForest & Sandy Lake Wastewater Lift Stations
Shop Drawing Review Comments
DeForest Construction Schedule
Sandy Lake Construction Schedule
Schedule of Values
TCB has the following comments on these submittals:
Description Status Comment
DeForest Construction No Exceptions Take --
Schedule
Sandy Lake No Exceptions Taken --
Construction Schedule
Schedule of Values Make Corrections Noted Sum of Bid Items 2 & 8 = $1,849,600
Total in Can-Fer Bid - $1,843,000
Adjust Schedule of Values <$6,600>
Sum of Bid Item 3 - $32,700
Total in Can-Fer Bid - $35,000
Adjust Schedule of Values +$2,300
Sum of Bid Item 9 = $20,700
Total in Can-Fer Bid - $25,000
Adjust Schedule of Values +$4,300
When you re-submit the shop drawings, please address all comments and submit eight (8) copies to
this office.
Distribution:
[X] 2 copies of submittal to the City
[X] 4 copies of submittal to Can-Fer Construction Company, Inc.
[X] 2 copies of submittal to TCB file
[ ] Other