RC Townhomes-CS050218T H E C I T Y O F
COlVFELL
February 18, 2005
Jason R. Rose
Rose Development
410 Spinnaker Drive
Allen TX 75013
RE: Riverchase Townhomes
Site Visit
Dear Mr. Rose:
A site visit ~vas conducted on February 17, 2005 at 10:15 a.m. I observed the lime crew in the
process of shaping the roadway, preparing for the application of lime to the subgrade. There was
no visible means of verifying the proposed subgrade elevations onsite. As you are well aware by
referring to the approved Construction Plans, there are critical grade areas inside the proposed
roadway bed, i.e. the storn~ drain crossing, the sanitary sewer main and sanitary sewer services.
My concern has been and is still the verification of subgrade elevations over those services to
prevent any damage from occurring.
From my site visit today, it would appear there is a good possibility that damage may have
occurred in some storm drain locations and possibly to some of the sanitary sewer facilities on
the east end of the project. My recommendation, once again, is that you verify all the horizontal
and vertical controls on the project, and verify the extent of damages, if any before proceeding to
paving operations. Please call me if there is any question about how to perform the needed
verifications.
Larry Davis
Construction Inspector
Office Phone: (972) 304-3684
Fax: (972) 304-3570
CC2
Keith R. Marvin, P.E.
Ed Heath, Quantum Contracting
JeffHarroun, Texas Site Excavation
Tarden Concrete
Ron Lustig, Coppell Townhomes LLC