ST9302-CS 980309SANDY LAKE - FROM DENTON TAP TO MACARTHUR BLVD CATEGORY NUMBER OF L.F. CONST. LOWER/RELO $ SHUTDOWN PERIOD. DAYS 1. PAVING 6 3,300 1,131,900 CONFLICT 14 2. DRAINAGE 3 150 93,000 CONFLICT 3. STREET LIGHT 17 595 368,900 FOUNDATION CONFLICT The existing design requires lowering the entire li~it of 10, 160LF at a cost of $2.6 M. due to paving, drainage and streetlight foundation conflicts. The original 7 section lowerings of 5,370 LF, based on the proj .ec~. report dated 7/21/94 -[was to account for paving and drainage conflict, however requiring a mmlmum COVer Of 8 FT. dlle to the standard air valve design. NOTES AND ASSUMPTIONS: PAVING: 1.. The 6 section lowerings are at the following station (Paving Conflicts): 1.1 8+75 to 12+25 = 350LF 20+50 - New air valve installation to replace the existing AN 1.2 29+25 to 33+50 = 425LF 43+00 New air valve In-qallation to replace the existing AN 1.3 68+50 to 74+40 = 590LF 1.4'79+25 tO 86+50 = 725LF 1.5 95+00 tO 100+00 = 500LF 1.6 100+90 to 108+00 = 710LF Total = 3,300 LF ~ $343/LF, consisting of 17 bid items based on current pricez Page 1 of 3 O O 2. The shutdown period estimate was based on factfin~ conversations with Johnson Brothers, Bar Contractors, in-house design and construction personnel and a meeting with Distribution Division. Reference attached memo to M, Richman and 71+00. The new A/V system each will cost $16,000. incl. 2 manholes.. New air valves will be installed at stm 10+50, 20+50 (re-install), 33+00, 43+00(re-install), 4. A new configuration for the Air Valve system will be utilized to minimiTe cover req~ to only 3.8 Ft. This Air Valve design was first installed in the Denton/Rossford project ex. 66" main in 1997. 5. Prior to fie-in, a total of 200,000 gal. dewatering will be accomplished with the inst~ of blow-off valves at low points. Note: Do not use greater,than 1300 GPM discharge pump. imment on the I~ion. or the 6. Two existing air valves not included in the lowerings will be re-installed using the new A/V design. DRAINAGE: 1. The 3 drainage conflicts are at station: 18+03, 21"RCP (1Ft. direct conflict) - Redesign may be possible 46+19, 21"RCP (4"clearance) - Redesign may be possible 55+40, 66"RCP (4FT. Direct conflict).- Lowering may be required or need major redesign 101+17 - Direct conflict with 27"RCP - Lowering no. 6 was extended by 110 LF !o acc~mmodat~ ltliS conflict and one streetiight foundation conflict Estimated Cost: $31,000/lowering, consisting of a total of 150LF pipe~ 300/LF and 6 closures ~ $8,000 each Page 2 of 3 @ STREET LIGHT FOUNDATIONS: The proposed street light 24" drilled shafts approximately 8 Ft. deep are in conflict at 24 different locations. However, 7 of these conflicts will be cleared in conjunction with the lowerings in item #1, leav/ng 17 conflicts to be cleared at the following stations: 1. 7+22 2. 14+92 3. 16+43 4. 24+89 5. 27+94 6. 36+72 7. 38+20 8. 39+76 9 42+75 10. 49+18 11. 52+58 12. 56+11 13. 57+65 14. 60+80 15. 64+20 16. 67+60 17. 94+64 Estimated Cost: $620/LF ( 35LF per relocation, total 595 LF) GENERAL NOTES: l. Special Provisions will be included to protect the existln~ main from heavy equipme~ during grading operations. Minimum 2.0fl. cover will be maintained to not allow total capacity to exceed 6600g/ft. Sheepsfoot rollers will not be permitted; skid boards will installed to distribute the load, etc. 2. Design Services est/mates approximately 4 weeks to complete in-house design for th~ lowerings. l 6 xt. load Jun Battad - 3/09/98 Page 3 of 3