ST9302-CS 980309SANDY LAKE - FROM DENTON TAP TO MACARTHUR BLVD
CATEGORY NUMBER OF L.F. CONST.
LOWER/RELO $
SHUTDOWN
PERIOD. DAYS
1. PAVING 6 3,300 1,131,900
CONFLICT
14
2. DRAINAGE 3 150 93,000
CONFLICT
3. STREET LIGHT 17 595 368,900
FOUNDATION
CONFLICT
The existing design requires lowering the entire li~it of 10, 160LF at a cost of $2.6 M. due to
paving, drainage and streetlight foundation conflicts.
The original 7 section lowerings of 5,370 LF, based on the proj .ec~. report dated 7/21/94 -[was to
account for paving and drainage conflict, however requiring a mmlmum COVer Of 8 FT. dlle to
the standard air valve design.
NOTES AND ASSUMPTIONS:
PAVING:
1.. The 6 section lowerings are at the following station (Paving Conflicts):
1.1 8+75 to 12+25 = 350LF
20+50 - New air valve installation to replace the existing AN
1.2 29+25 to 33+50 = 425LF
43+00 New air valve In-qallation to replace the existing AN
1.3 68+50 to 74+40 = 590LF
1.4'79+25 tO 86+50 = 725LF
1.5 95+00 tO 100+00 = 500LF
1.6 100+90 to 108+00 = 710LF
Total = 3,300 LF ~ $343/LF, consisting of 17 bid items based on current pricez
Page 1 of 3
O O
2. The shutdown period estimate was based on factfin~ conversations with Johnson Brothers,
Bar Contractors, in-house design and construction personnel and a meeting with Distribution
Division. Reference attached memo to M, Richman
and 71+00. The new A/V system each will cost $16,000. incl. 2 manholes..
New air valves will be installed at stm 10+50, 20+50 (re-install), 33+00, 43+00(re-install),
4. A new configuration for the Air Valve system will be utilized to minimiTe cover req~
to only 3.8 Ft. This Air Valve design was first installed in the Denton/Rossford project
ex. 66" main in 1997.
5. Prior to fie-in, a total of 200,000 gal. dewatering will be accomplished with the inst~
of blow-off valves at low points. Note: Do not use greater,than 1300 GPM discharge
pump.
imment
on the
I~ion.
or the
6. Two existing air valves not included in the lowerings will be re-installed using the new A/V
design.
DRAINAGE:
1. The 3 drainage conflicts are at station:
18+03, 21"RCP (1Ft. direct conflict) - Redesign may be possible
46+19, 21"RCP (4"clearance) - Redesign may be possible
55+40, 66"RCP (4FT. Direct conflict).- Lowering may be required or need major
redesign
101+17 - Direct conflict with 27"RCP - Lowering no. 6 was extended by 110 LF !o
acc~mmodat~ ltliS conflict and one streetiight
foundation conflict
Estimated Cost: $31,000/lowering, consisting of a total of 150LF pipe~ 300/LF and 6
closures ~ $8,000 each
Page 2 of 3
@
STREET LIGHT FOUNDATIONS:
The proposed street light 24" drilled shafts approximately 8 Ft. deep are in conflict at 24
different locations. However, 7 of these conflicts will be cleared in conjunction with the
lowerings in item #1, leav/ng 17 conflicts to be cleared at the following stations:
1. 7+22
2. 14+92
3. 16+43
4. 24+89
5. 27+94
6. 36+72
7. 38+20
8. 39+76
9 42+75
10. 49+18
11. 52+58
12. 56+11
13. 57+65
14. 60+80
15. 64+20
16. 67+60
17. 94+64
Estimated Cost: $620/LF ( 35LF per relocation, total 595 LF)
GENERAL NOTES:
l. Special Provisions will be included to protect the existln~ main from heavy equipme~
during grading operations. Minimum 2.0fl. cover will be maintained to not allow total
capacity to exceed 6600g/ft. Sheepsfoot rollers will not be permitted; skid boards will
installed to distribute the load, etc.
2. Design Services est/mates approximately 4 weeks to complete in-house design for th~
lowerings.
l
6
xt. load
Jun Battad - 3/09/98