Ballet TX-CS050414cOPPELL
April 14, 2005
Ken Head
Head Construction Inc
3030 LBJ Frwy Ste 700
Dallas TX 75234
fax 214-722-7635
RE: Ballet Academy of Texas
Dear Mr. Head:
A pre-construction conference on the referenced project has been scheduled for Tuesday,
April 19, 2005 at 2:00 p.m. in the Lobby conference room in Town Center at 255
Parkway Blvd.
Please notify the franchised utility companies, contractors, sub-contractors, testing lab
and any other interested parties so that they may have a representative present. If you
have any questions concerning this project prior to the scheduled meeting, feel free to
contact me at (972) 304-3684.
ti
Larry Davis, Construc 'on Inspector
Office Phone: 972-304-3684
Fax: 972-304-3570
CC:
Ken Griffm, Director of Engineering & Public Works
Glenn Hollowell, Asst. Director of Public Works
Greg Jones, Chief Building Official
Lee Stone, Commercial Building Inspector
Tim Oates, Fire Marshal
See Page 2
255 PARKWAY ~ P.O BOX 478 ~ COPPELL TX 75019 ~ TEL 972/462 0022 1~ FAX 972/304 3673
RESPONSIBILITY FOR PRE-CONSTRUCTION
MEETING NOTIFICATION
2
The owner / owner's representative will be notified of the date, time and place of
the pm-construction meeting once it is scheduled by the Construction Inspector
assigned to the project.
It is the owner / owner representative's responsibility to notify the following
parties:
· Franchise Utilities (including but not limited to electric, gas, cable, &
telephone providers)
· Geotechnical firm
· Project Engineer
· Contractors or subcontractors for excavation, utility, & paving operations
· SWPPP representative