Listed for your review and consideration are the items we discussed earlier by phone. Subsequent to the
good faith effort made to address the known deficiencies associated with the pavement on the referenced
project, other areas of concern have developed. They are located as follows:
1. Westbound, west of Lodge Rd.
2. Westbound, west of London Way.
3. Eastbound at Dobecka Dr.
4. Eastbound, west of Highland Meadow.
5. Eastbound at Meadow Run.
Additionally, the requirements outlined in Section Six of the contract documents relative to "Record t_ ~,,
Documents" have not been met. Lc~6, 4~ i~~ ?,~.~ 5~ ~' ~Scj 3 iv~ ,3 ~
Lastly, the final quantities of some bid items need reviewing. I~1 co~n_tr_act.__Fr~e, i_[e~.s~.~u__mbered
40, 43, 47, 50, 51, 80 ~l~__9fi~agd 94 ~~ler ~L2~Ihe 67 sched,l.e~40 b. or~the 2" sched_~_ul.eD
4~o~ cut,jin Chh~e Order #5 items numbered 36, 39, 41 and 42. Most of these issues are minor and
can be q'~i~ly resolved.
Welcome back. I hope to hear from you soon.
Sincerely,
Garr~tffCampbell/Sr.
Construction Inspector
cc: Ken Griffin, Director of Engineering/Public Works
1055.200~'
':/: ,
!,
T H E C I T Y · O F
COpPELL
April 14, 2005
Mr. Robert Weber, Project Manager
Ed Bell Construction Co.
10605 Harry Hines Blvd.
P.O. Box 540787
Dallas, TX 75354-0787
Re: Sandy Lake Road Project # ST 93-02
Dear Robert:
Listed for your review and consideration are the items we discussed earlier by phone. Subsequent to the
good faith effort made to address the known deficiencies associated with the pavement on the referenced
project, other areas of concern have developed. They are located as follows:
1. Westbound, west of Lodge Rd.
2. Westbound, west of London Way.
3. Eastbound at Dobecka Dr.
4. Eastbound, west of Highland Meadow.
5. Eastbound at Meadow Run.
Additionally, the requirements outlined in Section Six of the contract documents relative to "Record
Documents" have not been met.
Lastly, the final quantities of some bid items need reviewing. In the original contract are items numbered
40, 43, 47, 50, 51, 80, 81, 93 and 94, in Change Order #2 the 6" schedule 40 bore and the 2" schedule
40 open cut, in Change Order #5 items numbered 36, 39, 41 and 42. Most of these issues are minor and
can be quickly resolved.