Loading...
WA0101-CS050328Mr. Jim Cummings FWRM, Inc. P.O. Box 6173 San Antonio, Texas 78209-0173 March 28, 2005 RE: S.H. 121 Water Line / WA 01-01 Permanent Water Line Easement / Temporary Construction Easement Dear Mr. Cummings: This letter is a follow-up to Suzan Taylor's March 16, 2005 conversation and e-mail concerning the acquisition of additional permanent and temporary water line easements from your property located in the vicinity of S.H. 121. The design plans did not take into account the location and size of the bore pits required to install the water line across S.H. 121. During the pre-bid meeting, comments from potential bidders prompted the consultant to reevaluate the number and size of easements required. The additional permanent water line easement is contiguous with the west line of the previously dedicated 20-foot easement. The water line is 30 foot deep in this area and the easement will provide sufficient area for operations and maintenance of the water line should it ever have to be exposed. The easement will have limited impact upon future development of the property since it is located within the 30-foot side yard and the 60-foot front yard setbacks required of property zoned Highway Commemial. The City of Coppell is offering $0.88 per square foot for the permanent water line easement. Permanent utility easements are usually acquired at one-half of the land value as shown in the Dallas Central Appraisal District. The temporary construction easement located on the south side of S.H. 121 is needed for the installation of a receiver bore pit. Temporary construction easements are not filed with Dallas County and will expire upon completion of the project. The value is established based on a 'temporary lease' at a 5% return to the owner. This letter constitutes an offer from the City of Coppell for the acquisition of the easements as follows: 1. Permanent water line easement at $.88/sq. ft. x 169 sq. ft. 2. Temporary construction easement at ($.88/sq. fl. x 457 sq. ft.) x 5% Total $148.72 20.15 $168.87 The city is scheduled to open bids on March 24 and award the contract during the April 12, 2005 City Council meeting. Enclosed are copies of the easement documents. If the above offer is acceptable, please sign below and retum to this office. Once the letter is received, the process for payment of the $168.87 can start. When the check is ready, we can arrange a mutually agreeable method to exchange the documents and the check. You consideration of this matter is appreciated and should you have any questions, please contact Suzan Taylor at 972-304-7019 or me. Sincerely, £~ Director of Engineering/Public Works Office: 972/304-3686 Fax: 972/304-7041 E-mail: kgriffin(~ci.coppell.tx.us Enclosures James H. Cummings IN ACCEPTANCE David K. Cummings Date Date