Coppell Trade-CS050503 T H E C I T Y O F
coPPELL
May 3, 2005
Rick Stull
McFadden & Miller
Fax: 972/401-1399
RE:
Coppell Trade Center, Lot Block 1 - REVISED TIME
Pre-construction Meeting for Paving, Fire Riser, FDC Line, Domestic &
Irrigation Meters
Dear Mr. Stull:
A pre-construction conference for the referenced project has been scheduled for
Thursday, May 5, 2005 at 3:00 p.m. in the first floor conference room in Town Center at
255 Parkway Blvd.
Please notify the franchised utility companies, contractors, sub-contractors, testing lab
and any other interested parties so that they may have a representative present. If you
have any questions concerning this project prior to the scheduled meeting, feel free to
contact me at (972) 304-3684.
Sincere
arry avis, Construction spector
Office Phone: 972-304-3684
Fax: 972-304-3570
CC:
Ken Griffin, P.E., Director of Engineering & Public Works
Glenn Hollowell, P.E., Asst. Director of Public Works
Greg Jones, Chief Building Official
Lee Stone, Commercial Building Inspector
Tim Oates, Fire Marshal
A1 Sorrels, Holt Lunsford
Dayton Macatee, P.E., Macatee Engineering
Paul Bosco, Metro-Plex Underground
See Page 2
255 PARKWAY ~i, p o BOX 9478 ~i, COPPBLL TX 75019 ,# TEL 972/462 0022 ~ FAX @72/3O4 3673
RESPONSIBILITY FOR PRE-CONSTRUCTION
MEETING NOTIFICATION
The owner / owner's representative will be notified of the date, time and place of
the pre-construction meeting once it is scheduled by the Construction Inspector
assigned to the project.
It is the owner / owner representative's responsibility to notify the fo/lowing
parties:
· Franchise Utilities (including but not limited to electric, gas, cable, &
telephone providers)
· Geotechnical firm
· Project Engineer
· Contractors or subcontractors for excavation, utility, & paving operations
· SWPPP representative