ST9302-CS 981118 (2)From:
To:
Date:
Subject:
<tbranch 1 @tu.com>
Allegro5. Hub 05("richard.lorenz@tu.com")
11/18/98 10:41AM
Sandy Lake Road
The City of Coppell Engineering Department and the contractor for this
project will be walking the project this Friday morning, November 20, to
look at trees that will need to come down for this project. They will mark
those trees in paint with a "X". While this will include many of the trees
affecting the TU project, it may not, and probably will not, include all of
the trees affecting our work. We need to get together to walk the project
and look at tree trimming that will be needed for us to obtain proper
clearance for our facilities. We have told them we will be finished with
our portion in December, so we need to look at all we have to do to meet
this deadline and not hold up the road project. I will be out of the
office next week, so if you need to discuss this with me please feel free
to call.
CC:
Allegro5.Hub 05("binmon@tue.com")