Loading...
ST9302-CS 981001 (4)Project: Date: Time: CITY OF COPPELL, TEXAS PRECONSTRUCTION CONFERENCE AGENDA Sandy Lake Road Paving, Drainage, and Water System Improvements October 1, 1998 2:00 PM 1. PROJECT ADMINISTRATION A. Owner: City of Coppell 255 Parkway Blvd. Coppell, Texas 75019 Telephone: 972/304-3679 Fax: 972/304-3570 B. Contractor: Ed Bell Construction Company P.O. Box 540787 Dallas, Texas 75354-0787 Telephone: 214/358-6581 Fax: 214/352-3201 C. Engineer: Kimley-Horn and Associates, Inc. 801 Cherry Street, Suite 1100 Fort Worth, Texas 76102 Telephone: 817/335-6511 Fax: 817/335-5070 D. Project Contacts: Project Managers- Lee Allison, P.E. Paul Hames, P.E. Contractor's Contact-Michael G. DeMotte 2. CORRESPONDENCE/COMMUNICATION All written correspondence sent to either the Owner, Conuaetor, or Engineer shall be copied to all other parties. When referring to the project in correspondence, please include both the Kimley-Hom project number 06940600 and the City of Coppell project number ST 93-02. 3. NOTICE TO PROCEED Pursuant to SC 1.16 a Notice to Proceed will be given to the Contractor. The contractor agrees to begin construction within 10 calendar days after the date of the Notice to Proceed and complete construction within 850 calendar days as indicated in the Notice to Proceed. Any adjustment required to the above shall be handled by Change Order. 4. CONSTRUCTION LAYOUT See SPR 1.9. 5. CHANGE ORDER See GC 1.37.1. Any changes or deviations from the plans and specifications for the project requiring additional ~o~.1~.. ction time shall be handled by Change Order. All Change Orders will be ~ by the Contractor, Project Engineer and Owner. In submitting Change Orders, please provide three copies for distribution. Any changes or deviation from the plans and specifications not requiring additional funding or construction time will be handled by a Field Change. Field Changes shall be reviewed by the Engineer and approved by the City. 6. EXTENSION OF TIME See SC 1.36. 7. DRAWINGS AND SPECIFICATIONS The Contractor has been given five (5) sets of project pla,xq and specifications. Record drawings are to be maintained at the project site by the Contractor, and submitted to the Engineer upon completion of the project (see SS 01720) 8. CONTRACTOR'S ESTIMATE See SS 01310. Prior to submitting Application for Payment to Engineer for review, the Contractor shall verify that record documents have been updated to reflect variations from the "As Bidn drawings up to the date for which the Contractor seeks payment. The schedule for submitting payment requests is to be discussed. 9. GENERAL UTILITY NOTE The CONTRACTOR shall be responsible for locating all utilities, whether private or public, prior to excavation. The information and data shown with respect to existing Underground Facilities at or contiguous to the site is approximate and based on information and data furnished by the owners of such Underground Facilities or on physical appurtenances observed in the field. The OWNER and Engineer shall not be responsible for the accuracy or completeft~s of any such information or data; and, the CONTRACTOR, shall have full responsibility for reviewing and checking all such information and data, for locating all Underground Facilities, for coordination of the Work with the owners of such Underground Facilities during construction, for the safety and protection thereof, and repairing any damage thereto resulting from the Work, the cost of all of which will be considered as having been included in the Contract Pi'ice. The CONTRACTOR shall notify any affected utility companies or agencies in writing at least 48 hours prior to beginning construction. 10. BARRICADES AND PUBLIC PROTECTION The Contractor shall be responsible for barricades, barricade maintenance and public protection at all hours. After hour hazards appearing at the construction site shall be remedied immediately, upon notification. 11. ADDITIONAL WORK Any additional work performed by the Contractor not covered by the scope of this project, and without an approved change order, shall be at the sole expense of the Contractor. 12. AFFIDAVIT OF FINAL PAYMENT AND RELEASE At the completion of the project, and prior to the Final Pay Request, the Contractor shall submit to the Owner an Affidavit and Waiver of Lien and an Affidavit of All Bills Paid. 13. MAINTAINING ADJACENT PROPERTY See SPR 1.4, 1.13, 1.16, 1.19. Discussion of abatement of noise, dust and mud. 14. SUBCONTRACTING All items of work are the direct responsibility of the Contractor. There should be no direct communication between Subcontractors and either the Owner or the Engineer. 15. SHOP DRAWINGS AND SAMPLES The Engineer will review all submittals as quickly as possible, but does not guarantee that his review will be completed within any pre-established period of time. Should the Contractor include review time by the Engineer in his schedule of work, the Engineer assumes no responsibility for meeting this schedule. The Contractor shall submit 6 or more copies, 4 of which will be retained by the Engineer for distribution. All other reviewed copies shall be returned to the Contractor. 16. WORKING DAYS / HOURS Discussion of normal working days and hours. 17. PERMITS Discussion of applicable permits. · ~..~'~'~' .---~ ~ 18. TESTING "'", ~e~'w'x- / See SPR 1.11. ~ Q,~t~ iH ;'~'~,.0_ 19. CLEAN-UP-DAILY See SPR 1.19. 20. TRAFFIC CONTROL Discussion of impact of construction on access to businesses along construction route, emergency access (fire and police), school access and traffic management plan. 21. PUBLIC RELATIONS Discussion of general public relations issues including the importance of publicity and responsiveness to citizen concerns. Information on this project will be freely distributed to the citizens of Coppell. Methods of distributing this information will include the City of Coppell website (interne0, a telephone hofline, bi-weekly newsletters, meetings with Home Owners Associations, and informative BBQs. The importance of friendly, responsive interaction between the Contractor's on-site representatives and the citizens of Coppell cannot be over-emphasized. 22. APPROACH/SCHEDULE/PHASING OF WORK 23. FIELD OFFICE 24. SW CORNER OF HEARTZ/SLR PROPERTY STATUS/SENSITIVITY 25. LONE STAR GAS CONFLICT RESOLUTION 26. FRANCHISE UTILITY RELOCATIONS 27. TU CONDUIT - REQUEST FOR PRICES 28. MONTHLY STATUS MEETINGS 29. WEEKLY COORDINATION MEETINGS 30. DWU COORDINATION 31. 30" DWU SHUTDOWN COORDINATION W/UTRWD AND FLOWER MOUND 32. CITY OF COPPELL COMMENTS 33. QUESTIONS