ST9703-CS050601 (2)COP?ELL
June 1,2005
Marty Murphy, Business Manager
JRJ Paving L.P.
2277 Masch Branch Road
Denton, TX 76207
MacArthur Boulevard Widening (from Bethel School Rd. to Belt Line Rd.)
Project # ST 97-03
NOTICE TO PROCEED WITH CONSTRUCTION
Dear Mr. Murphy:
This letter will serve as your official notice to begin work on the referenced project. For
purposes of the contract, your calendar days will start June 6, 2005. If you should begin
work prior to that date, then the calendar days will commence on the day work begins.
Seventy-five (75) calendar days were bid on this project for completion of work. Therefore,
if work begins on June 6, 2005, then the calendar days on the project will expire on August
19, 2005. The liquidated damage policy concerning the closure of the lanes still applies as
per the contract documents.
If you have any questions or need any additional information please feel free to contact Rick
O'Dell, Construction Inspector at (972) 304-7090.
Sincerely, th
Kenneth M. Griffin, P.E.
Director of Engineering & Public Works
Office 972/304-3686
Fax 972/304-7041
E-mail kghffin~ci.coppell.tx.us
cc: Rick O'Dell, Construction Inspector