Villas at LV-CS050602 T H E C I T Y O F
COPPELE
June 2, 2005
Daniel L. Heischman, P.E.
Dowdey, Anderson & Associates
5225 Village Creek Dr., Suite 200
Piano TX 75093
RE: Villas at Lake Vista, Phase 1
Dear Mr. Heischman:
A pre-construction conference on the referenced project has been scheduled for Tuesday,
June 7, 2005 at 10:00 a.m. in the 1st floor conference room in Town Center at 255
Parkway Blvd.
Please notify the franchised utility companies, contractors, sub-contractors, testing lab
and any other interested parties so that they may have a representative present. If you
have any questions concerning this project prior to the scheduled meeting, feel free to
contact me at (972) 304-7090.
Sincerely,
Rick O'DclI, Construction Inspector
Office Phone: 972-304-7090
Fax: 972-304-3570
CC:
Kcn Griffin, Director of Engineering & Public Works
Glenn Hollowell, Asst. Director of Public Works
Grog Jones, Chief Building Official
Lee Stone, Commercial Building Inspector
Tim Oates, Fire Marshal
Rodney Louviere, Dowdey Anderson & Associates
RESPONSIBILITY FOR PRE-CONSTRUCTION
MEETING NOTIFICATION
The owner/owner's representative will be notified of the date, time and place of
the pre-construction meeting once it is scheduled by the Construction Inspector
assigned to the project.
It is the owner/owner representative's responsibility to notify the following
parties:
· Franchise Utilities (including but not limited to electric, gas, cable, &
telephone providers)
· Geotechnical firm
· Project Engineer
· Contractors or subcontractors for excavation, utility, & paving operations
· SWPPP representative