Historic Coppell-CS050602DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
iTEM: JUNE 2 DRC (WITH APPLICANT) ONLY:
PD-108R6-H~ Historic Coppell Properties~ Ltd., zoning change request from PD-108-
H (Planned Development-108-Historic) to PD-108R6-H (Planned Development-108
Revision 6-Historic), to attach a Detail Site Plan to allow the developmefit of two
medical office buildings totaling 32,995-square feet on approximately 3.3 acres
ofI
property located along the south side of Bethel Road, approximately 185 feet east of
I
Coppell Road, at the request of Roger (Skip) Blake, Blake Architects.
STAFF REP.: Matt Steer PROJECT ID# PD-05-0017
9RCDATE: May 26, 2005 and June 2, 2005
CONTACT: Kenneth M. Gri~n, P.E., Dir. o[ En~ineerin~/Public Works 972/304-3686
COMMENT STATUS: ~PRELIMINARY FINAL 1gEV-tEED
.~TER P&Z
No comments.
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM: JUNE 2 DRC (WITH APPLICANT) ONLY:
Historic Coppell Properties~ Ltd, Addition~ Lots 1 and 2~ Block 1r Minor Plat, to allow
the development of a 16,677-square-foot medical office building on Lot 1 (Phase I),
containing 1.615 acres of property, and a 16,318-square-foot medical office building on
Lot 2 (Phase II), containing 1.641 acres of property, located along the south side of
Bethel Road, approximately 185 feet east of Coppell Road, at the request of Roger
(Skip) Blake, Blake Architects.
STAFF REP.: Matt Steer PROJECT ID# MP-05-0018
DRCDATE: May 26, 2005 and.lune 2, 2005
CONT~4CT: Kenneth M. Grilf~n, P.E., Dir. of En~ineerin~/Public Works 972/304-3686
COMMENT STATUS:__,~PRELIMINARY FINAL
Preliminary Utility Plan
1. Provide a manhole or clean-out, as appropriate, where the private sanitary sewer
meets the public system.
2. Coordinate the future connections to Coppeli Road with the easements dedicated on
the plat.